what is the problem not getting 7 days slab cycle in Mivan
formwork? what is the output of mivan carpenter per day?
Answer Posted / er nitin lahane
Per day work for 1 carpenter is minimum 10 sqm per, I.e your shuttering area is 3250sqm you completed work in one day you are required 325 carpenter.you complete work in 8 day you required 40 carpenter per day. Ok
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
how to disign cuplock shuttering and it's matireal requirement snd any related web site
Define What is the meaning of a blue land surveyors flag?
Can inverted beams used in pipes during construction? If yes, explain how it can be implemented?
For Wet Mix Mecadam design what is Optimum moisture content
WHAT IS THE CAUSES OF RUTTING ON FLEXIBLE PAVEMENT?
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork
What are the different theories of failure under static load?
What is the basic difference between OPC
Volume of 25kg putty bag & 40 kg putty bag volume??
what is education Cess.
1.Why we are preferring 43 grade cement than 53 grade cement. 2. Approximate cost difference between 43 and 53 grade cement. Thanks.
Why is the use of granular sub-base in concrete carriageways not preferred, explain?
how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...
Why Vitrified tile are getting pop up.