what is the problem not getting 7 days slab cycle in Mivan
formwork? what is the output of mivan carpenter per day?

Answer Posted / er nitin lahane

Per day work for 1 carpenter is minimum 10 sqm per, I.e your shuttering area is 3250sqm you completed work in one day you are required 325 carpenter.you complete work in 8 day you required 40 carpenter per day. Ok

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how much need cement bags for block work of wall approx 1000 hollow blocks 20x20x40cm

1637


For making a new road in a village having a school & hospital , tell the steps of construction systemically ?

1155


For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?

1330


In earth work 1300 cum soil how to calculate how many liters require in water

1991


is there any codal provision for soil cousion over the Hume pipe of Dia 1.2 m.

1568






silt%= silt volume/ silt+sand volume is this right?

1496


How do you determine specific gravity of cement?

689


What is the difference between EPC,DBOOT and BOOT.

23323


what is the cost differene of a same structure when it is constructed with brick masonary, and when it is constructed with concrete as a frame structure.????????

1465


What is the maximum crushing load in Kg & crushing strength in N/mm2 for M25 & M 15 Grade concrete

6241


In tower foundation, on the time of 3 mtr pit RCC casting if water and mud is their surface of PCC then what will be do?

1984


five benefits of using standard terminology in the measurement process

2853


How to take labor charges for construction of 1cum of concrete?

667


Explain the advantages and disadvantages of using plastic and timber fenders?

706


What is the difference between shear and tensile strength?

648