curing duration
Answers were Sorted based on User's Feedback
Concrete will give strenght after completion of reactions
in cement .The concete will give 67 % strenght in 7 days
75% Strenght in 14 days 98% strenght in 28days and 100 % in
one year.so we have to cure concrete for a minimum period
of 28 days for complete the reactions in cement and get
strengh
| Is This Answer Correct ? | 75 Yes | 16 No |
According to hydration process and strength gaining process
of cement 28 days curing is required but according IS code
of opc cement 7 days curing is required and in ppc 14 days
of curing is required. But above of all continuous curing
is very important for any construction instead of how many
days we cure it.
| Is This Answer Correct ? | 24 Yes | 5 No |
Answer / girish kumar v k
Gentlemen there is nothing Technical behind the concept of Curing.Logic is what behind this.
As per IS 456, the grade of the concrete itself indicates the strength of the Concrete after 28 days,..right?
Then curing has to be done for 28 days in order to test the Compressive strength of the concrete.
What I would say is.. without curing for 28 days how can you carry out the test and say that the member which contains the concrete equals the strength that off the cube strength. This concept is purelly Illogical.
To ensure whether the member has attained strength, cubes have to be kept on/adjacent to that particular member (Slab, beam,girder,column) and then curing to be carried out. Now curing will happen equally and simultaneoulsy to both.
Afterwhich testing of cubes will actually give the strength of the member
Else If curing is done for 7/14 days then test the cubes only for that particular period, which also signified same strength for the member.
But curing for 7/14 days only would lead following
1. Low compressive strength then required as per Design mix
2. Lesser durability of concrete
3. Increased permeability
4. Concrete becomes brittle & breaks due to improper hydration.
| Is This Answer Correct ? | 18 Yes | 3 No |
wha is frog?
I need model question papers for writing the Dubai municipality exam,for G+1
What is critical path method (c.p.m)?
all engineering filed in which branch mother branch
22 Answers L&T, Manoj Pharma Ltd,
how to calculate weight of 1.8 cum of aggregate
For G+4 storied building having 76000 sft per each floor, can you prepare schedule in such a way that structure should be completed with in 41/2 months and finishing be completed with in 51/2 months?
give me the mix proportion for design mix concrete M 7.5 grade 1:4:8
how to calculate total cost for slab 35'×8'
what is meant by MIS report
How to calculate 45 degrees bend Steel bar length in Slab Reinforce ment
12 Answers JBS Builders, L&T, Rajarathnam Construction,
How many bags required for 1cum grouting?
Ultimate strength to cement is provided by which chemical?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)