Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what else we can add rather than admixture in concrete to
reduce the cement quantity?



what else we can add rather than admixture in concrete to reduce the cement quantity?..

Answer / md irshad anwer

Pozzolanic Materials such as Fly ash, Silica fume, Rice
husk ash or Ground Granulated Blast Furnace Slag

Is This Answer Correct ?    15 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

In two way slab where should we stop the work at end of the day?

2 Answers  


is there zone 6 for earthquake in india? on what basis the naming of the zones are done in variuos countries?

2 Answers  


what is ppc????

13 Answers   L&T,


How to find the concrete volume in sloped footing??? illustrate with example

1 Answers  


The Hinged and Roller support is same or differnt if it is differnt how does it differs

3 Answers   HCL,


in the footings first which reinforcement bar has to be layed as per desi

1 Answers  


7. Do you apply the skills and knowledge learnt at school in your work?

1 Answers  


Why compressive strength of only concrete cubes and cylinders tested ? why not other shapes?

1 Answers  


Explain the Strength of brick?

0 Answers  


In concrete mix, water is required . we tried in case of water we are used milk. what hapened

4 Answers   Gammon,


Respected Sir, I am from a hilly place called Darjeeling ,I have constructed house of 9 column out of which 4 of the column is under water , i have put rcc slab on top and on top of the rcc slab i have construced two room house with bricks and light roof , now i am planning to change the light roof with rcc slab for the two room, my main concern is will the column under water will hold the load of the new rcc slab coz it already 10 to 12 yrs old , i dont know what to do , can u advice me regarding this matter, weather to leave the upper floor roof light or make it rcc slab.(If i put the slab , it will require 45bags of cement and u calculate how much of steel and sand and pebbles) thanks with regard Anand

2 Answers  


what is the measure of slump

9 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)