1)What is Suggested type of cement for concreting at water,
for mass concreting and where the chaces of gettin attucked
by salt?
2)How many types of camber?
3)why we always preffer short column in case of residential
building?
4) Is there any advantages between the use of One way slab
& two way slab?
5)What shoul be the % of steel for R. C. C. perpose based
on volume & area ?
Answers were Sorted based on User's Feedback
Answer / sujeeth
1) Generally for concreting under water we use concrete of
grade M20 or above and use plasticizers which reduce the
setting time and most imptly concrete shud not be released
from a height above 1 to 1.5 meter.
4) In one way slab, reinforcement is designed in such a way
that load is taken only by main steel and the purpose of
distributed steel is only to keep mail steel in position.
Whereas in two way slab, steel design is made suchthat load
is distributed over sntire reinforcement.
5) %age of steel by area in RCC beams and columns must
be < 4% and exact % depends on design of the structure.
P.S : Post questions 1 by 1 so that ppl can mark write and
wrong ans differently
| Is This Answer Correct ? | 21 Yes | 6 No |
Answer / a. shunmugam
3)why we always preffer short column in case of residential
building?
Answer: The short column fails only by crushing whereas the
long column fails by buckling. The buckling action of a
column will takes place very quickly than crushing,that why
we always prefer short column for residential buildings
| Is This Answer Correct ? | 14 Yes | 1 No |
Answer / sjtbehera
Ans1. In marine structure M20 is used in PCC and M30 &
above is used in RCC
Ans2. I think camber which are provided in Road are three
type
1. Parabolic
2. Straight line
3. Combination of parabolic and straight
4.
Ans3. The short columns are fail by only crushing where as
long column fails by buckling action.
Ans4. One way slab & two way slab are design according to
their need. One way slab are used when ratio of length of
the room to its width is greater than 2. such slad are
designed to span along width of the room. Main
reinforcement along width of room and carried load and
distributions are right angled to main reinforcement.
In two way slab is used where length of room to
breadth is less than 2 . in this case reinforcement are
provided in both length and breadth of room.
Ans5. in the case of building % steel in the base of rcc
are used in following manner
1. footing – 6%
2. beam- 1 %
3. column – 1.2%
4. lintel- .6%
5. slab- .8%
6. staircase- .8%
| Is This Answer Correct ? | 12 Yes | 3 No |
Answer / baba lalin
3)in short column, Bending will be small.. it takes more
time to buckle
| Is This Answer Correct ? | 6 Yes | 1 No |
1.For mass concreteing PPC cement is perfered because Heat
of hydration of PPC is vry less compare to OPC, to avoid
thermal cracks.
Chances of attack by slat is chloride content in water
what the water used for concrete or the structure may
immeresed in sea water,or the structure may exposed near
costal
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / s p sharma
Q3:why we always preffer short column in case of
residential building?
Ans: To reduce the cost of construction.
Q3:Is there any advantages between the use of One way slab
& two way slab?
Ans: Two way slab is economical and allowable deflection is
more.
| Is This Answer Correct ? | 1 Yes | 1 No |
Answer / ketan
1)What is Suggested type of cement for concreting at water,
for mass concreting and where the chaces of gettin attucked
by salt?
ANS :- RHC/ SRC
UNDER WATER
3)why we always preffer short column in case of residential
building?
ANS:- TO GET MAX FSI W.R.T HEIGHT RESTRICTION
| Is This Answer Correct ? | 2 Yes | 3 No |
Can we use PPC cement for RCC works? Upto which grade it can be used?
what would be the rqmnt. of cement and sand (1:6)for building brick wall and also 20mm thick plaster on the wall by same ratio?
What is quantity of cement and sand required for 2000sqft of tiling?
Deshuttering time for slab 6.15 meter
1) what do you mean by rolling margin of steel ? 2)pls. tell the cut length formula of stirrups as per IS codes(take out cut length for a beam of 600*300mm with 40mm cover all sides)? 3)what is the multiplying factor of painting for sand faced plaster? 4)if your footing is of size1.9*1.6m . what quantity of length and width you will excavate means what extra margins you will allow as per IS codes in billing?
How much snowcem required per sq. Meter area
3 Answers Bhushan Power Steel,
How t find the quantity of materials required for construction of a wall of length 10x5x0.2
what is the water cement ratio? how to calculate it? list the wt. of constructions materials including concrete both ordinary and light wt. concrete
how to calculate the number of cement bags for basic construction..?
3 Answers Gammon, Indu Projects,
what is dead wall?
i) Distinguish between Theodolite and dumpy Level? (Marks-8) ii)Distinguish between Viscous and Turbulent flow? (Marks-8) iii) Distinguish between nominal and design mix? iv) What is standard sand? v) Explain the term plane stress? Vi) Differentiate between principal plane and principal axis? Vii) write short notes on Elastic limit of structural steel? viii) Write short notes on stress concentration? ix) write short notes on "Grading of Sand" ? x) How many grades of concrete are there under standard concrete?
0 Answers Public Service Commission,
how much steel is required for 1 sqft of slab
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)