Answer / pramod naik
the brick size are 0.19 X 0.9 X 0.9 i.e standard with morter it is 0.2 x 0.1 x 0.1,
Volume of One Brick =0.2 x 0.1 x 0.1
=0.002m3
No of Bricks in 1 cubic metre = 1/0.002
= 500 nos
| Is This Answer Correct ? | 4 Yes | 0 No |
Answer / veeramuthu
Brick Size = 190 x 90 x 90 mm
Volume of One Brick =0.19 x 0.09 x 0.09 m
= 0.001539 cum
No of Bricks in 1 cubic metre = 1/0.001539
= 649.77
= 650 nos (Approx)
| Is This Answer Correct ? | 10 Yes | 15 No |
Answer / kaushik shah
if the brick size are 0.19 X 0.9 X 0.9 i.e standard size
then 550 nos bricks are required (including wastage) in 1 m3
| Is This Answer Correct ? | 0 Yes | 8 No |
WET BULB TEMPERATURE AND DRY BULB TEMPERATURE?
1m3 of brick is equal to how many cft of brick
how can i test sand on field in lebortry?.
how to calculate the steel for rcc slab 1100 Square feet
sir my site not availabele 12mm steel now if i use 10 mm how many spacing require for slab design slab thk 200mm footing, column,raft,wall how can calculate give me formula
how to calculate the no. of brick (18'*9'-wall)
Providing and fixing in position Tor steel to footings, foundation, slabs, beams, columns, canopies, stair case, newels, chajjas, lintels, etc. including cutting, bending, hooking the bars, binding with wires. give me the rate M.ton.
how to find the cement and sand quantity for wall plastering
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2
0 Answers First American Corporation, GS Infra, L&T, Real Sociedad,
ratio 1:4:8: for pcc. area 1008 cft. thickness 6' what is the quantity we need
Pls help me to arrive the rates for centering shuttering for highbay using H-frames?
How do You Maintain a structure after getting cube test of low strength.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)