Answer / biv05

lapping is provided when the main steel is generally not enough for the span I.e more than 12 m r/f is provided
for 8 mm -400mm
10mm-500mm
12mm-600mm
16mm-800mm
20-1200mm
DEVELOPMENT LENGTH: is the length of the vertical steel generally taken as a L shape ..this length is critical as compression is higher on this point ..
formule: l*d 10d

Is This Answer Correct ?    3 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

how many average of shuttering in one cubic meter concrete

5 Answers  


Define Workability ?

0 Answers  


For 100 bag cement how i will calculate sand and metal aggregate.Mixing proportion 1:1.49:2.38

1 Answers  


I had a plot of say 5000 sq.ft. and soil in the plot is normal soil. Now I had to work upon the tender quantities to prepare a preliminary budget within a day. Is there any thumb rule or assumptions to calculate the quantities which can differ upto 15% +/-?

2 Answers  


what is scaffolding and state is purpose

8 Answers  






what is the painting co efficient of slope roof tiles?

0 Answers  


wat is the quntities of cement and sand for 10msquer wii plastering for 10mm tick

1 Answers  


How to calculate the cement, sand quantity for plastering? (10'x10')10mm thick ratio 1:5. wht"s the formula?

35 Answers   Adarsh Developers, Amrapali, Ganesan Builders, MAHINDRA, NCC, Olympia Infratech, Omex, Ozone Group, Papni Associates, Perfect Arts, PPEC, Raj Construction, Ramky, Skyline Builders, VRR Builders & Developers,


what is the relation between pitch of steel and depth of slab?

0 Answers   RBI,


How to find the cuplock pipe qty in staging for Minor bridge?

0 Answers  


What is meant by autocad?

0 Answers  


Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting

0 Answers   Vishal Pipeline And Engineering,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)