Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


1.how to calculate 4*3 runner qty in cft.
2.how to calculate the nails qty.(column,beam,slab)
3.if any formula for binding wire qty calculation.



1.how to calculate 4*3 runner qty in cft. 2.how to calculate the nails qty.(column,beam,slab) 3.if..

Answer / ratheesh

1. First you have to convert inches to feet, 1 inch =
.083feet, Then u have to multiple length, breadth & width.

2. approximate .750grms to 1kg for 1 sqm shuttering.

Is This Answer Correct ?    4 Yes 3 No

Post New Answer

More Civil Engineering Interview Questions

calculate the cost for AAC block wall of 15cum?

2 Answers  


How manu days after the casting of a slab another slab can be casted above it? what is the total curing time of a slab if ponding is not done on it?

6 Answers  


among fine,coarse sand which is used for plaster, brickwork and RCC & why?

2 Answers  


Will going from a 3-tap to 6-tap increase water pressure?

0 Answers  


What is the diffrence between plinth/basement and plot area

1 Answers  


08. 4 main points about check list for Shuttering works are––– 4 i) ii) iii) iv) 09. 4 main points about check list for Concreting works are––– 4 i) ii) iii) iv) 10. 4 main points about check list for Plaster works are––– 4 i) ii) iii) iv) 11. 4 main points about check list for Brick works are–– – 4 i) ii) iii) iv) 12. 3 main points about Project delaying factors are––– 3 i) ii) iii) 13. Write down 60-grade M.S. deformed bar specification. 3 14. 3000 psi concrete means: 1 15. 4 main points about methods of wastage control are–– – 4 i) ii) iii) iv) 16. 1 main point about reasons for your honesty is : 1 17. Water cement mixing in hopper less mixture machine is better than hopper mixture machine because: 1 18. 2 main points about your role during roof casting are–––– 2 i) ii) 19. a. The weight of 3333m deform bar of 24.5 mm dia is…… 1 b. The weight of 300 rft plain bar of dia 1&#61618; is……. 1 20. The types of slumps are––– 3 i) ii) iii) 21. 4 main points about the causes of cylinder failure are––– 2 i) ii) iii) iv) 22. Detection of a beam & a girder are–––– 2 i) ii) 23. Curing is needed for–––– 1 24. The types of slabs in respect of size & shape are––– 5 In respect of size: i) ii) In respect of Shape i) ii) iii) 25. The types of Column in respect of size & shape are–– – 9 In respect of size: i) ii) In respect of Shape: i) ii) iii) iv) v) vi) vii) 26. 3 field tests & 3 Laboratory tests of bricks are––– 6 Field tests: i) ii) iii) Lab test: i) ii) iii) 27. 2 field tests & 1 Laboratory tests of sand are––– 3 Field tests: i) ii) Lab test: i) 28. 1 field tests & 1 Laboratory tests of M.S rod are––– 2 Field tests: i) Lab test: i) 29. a. The % of water absorbs by brick chips: …………… 1 b. The % of water absorbs by Stone chips: …………… 1 30. In respect of design: 5 a. The % of strength gains by concrete in 28 days= b. The % of strength gains by concrete in 14 days= c. The % of strength gains by concrete in 07 days= d. The % of strength gains by concrete in 03 days= e. The % of strength gains by concrete in 28 days without curing =

3 Answers  


what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??

0 Answers  


What is the Oneday Productivity for 1 Skilled Carpenter and 1 Steel fixer?

2 Answers   GP Construction,


How much time Required for PPR pipe network testing

0 Answers  


how to determine the correctness of proportion used in cement mortor and various IS codes to determine the same?

0 Answers  


What are the tests required to check the Quality of steel?

6 Answers  


extra how much quantity need to fill the actual excavated quantity.

4 Answers   L&T, Mechanical,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)