what are the steps to commissioning a DCS system?
Answers were Sorted based on User's Feedback
Answer / dhanraj suman
1. Panel alignment.
2. Power up DCS with electrical wiring checking.
3. Checking of proper grounding/earthing.
4. Preliminary Electrical I/O testing.
5. Instrumentation Loop checking.
Is This Answer Correct ? | 36 Yes | 1 No |
Answer / aswini ku sahoo
1-proper allignment of pannel
2 power cable laying from UPS DCDB
3-Checking of proper grounding or earthing
4 Negtive terminal of sup. Vol shuold be zero potential.
and then connect the power cable with proper polarity.
5 U r now almost ready to switch on the pannel but now
one imp thing is to disconnect all AI/AO CARD connector
6 All connector pin should not be sort with the ground.
7 Now swith on the pannel
8 Next UTP cable laying work from DPU TO HMI.
9.Agfter proper connection of UTP ping the system
with priper IP addresss.
10 .now start loop cheching and one by one signal throwing
10.Aftr then one by one
Is This Answer Correct ? | 2 Yes | 0 No |
what is hot loop check and cold loop check.
3 Answers Bapco Bahrain Petroleum Company,
Can we measure pressure using differential pressure transmitter? If yes then how?
why we use condesiate parts before tranmitters?
What is meant by cold float of compressor shaft.
Define all the process Variable and state their unit of measurement. ?
Exapain Deatails of the PID controlller
i want know about capillary type LT transmitter installation. we can install any location in between to HP and LP leg?
why micro controller 8051/52's clock frequency is internally divide by 12 ?? and why it is further divide by 32 in UART serial communication ??
What is the difference between uv and ir scanners? and what is the workig principle of both
hi sir yhis is zahid ali i am preparing for the jspl at oct.4.please send me the recently updated sample paper.
please tell me how maintainence person shifted to good epc company/design company
in which mode of the zener diode act when load voltage is approximately constant