what are the steps to commissioning a DCS system?
Answer Posted / aswini ku sahoo
1-proper allignment of pannel
2 power cable laying from UPS DCDB
3-Checking of proper grounding or earthing
4 Negtive terminal of sup. Vol shuold be zero potential.
and then connect the power cable with proper polarity.
5 U r now almost ready to switch on the pannel but now
one imp thing is to disconnect all AI/AO CARD connector
6 All connector pin should not be sort with the ground.
7 Now swith on the pannel
8 Next UTP cable laying work from DPU TO HMI.
9.Agfter proper connection of UTP ping the system
with priper IP addresss.
10 .now start loop cheching and one by one signal throwing
10.Aftr then one by one
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is 1:1 redundancy ?
how to work static pressure sensore how to work dpt
Why we are using reverse action in displacer types level transmitters on some Vessels?
how do u calibrate the vacuum transmitter if it shows more reading
what is function of SCADA , and how is it work, explain with difination
How addressable fire systems work? Pl. send details with architect.(Loop), also send details regarding Gas system. Pl. help me.Thanks
Explain how thw analog to digital converter works with the circuit diagram
I have 0.75mm sq multicore cable (IS type) , can use instead of same type but 1.5 sq mm cable ? Note : The distance is around about 150 meter.
Meaning of the following a. IOP- Manimum; b. IOP- Maximu,;
DEAR SIR/MADAM MY NAME IS ARKAPROVA BHATTACHARYYA.I AM A FRESHER INSTRUMENTATION ENGINEER.CAN YOU PLEASE SEND SOME QUESTION PAPERS OF GRADUATE ENGINEER TRAINEE EXAM OF DVC(DAMODAR VALLY CORPORATION).MY EMAIL IDs ARE arka_aec@rediffmail.com.
How you calibrate absolute pressure with the calibration range of 0 to 1000 0C Absolute. Please explain the procedure for calibration.
how to commission furnace ( water heater)
Describe the function of Accumulator into the Pump
how do calibrate the valves.. with clear manual
Boolean algebra