what is post close & pre close of trip circuit supervision
relay in circuit breaker control scheme?
Answers were Sorted based on User's Feedback
Answer / ashish patil
Preclose means breaker in off condition it supervise the trip coil & trip ckt is healthy.
& Postclose means It supervise When breaker is ON.
| Is This Answer Correct ? | 43 Yes | 5 No |
Answer / k.prakashchandra
It will supervise the trip circuit before and after closing
the breaker
| Is This Answer Correct ? | 18 Yes | 5 No |
To measure insulation resistance of 11KV cable between core & armour, what should be the test voltage & duration?
what will be efficient rating of ac motor to lift a 10 kg wt of stone to 10 meter height with input 220V AC 50 Hz frequency???
Define the "All - Day Efficiency" of a Transformer
can any one tell me the formula for calculating the power and unit consumpetion
A 11KV, 1200 A breaker combination fixed in a cubicle for HT motor.Is normally for 11 KV motor fuse is using? if Yes, What range fuse is required?
Why the generating station rating is in KW though the rating of generators in KVA?
What will happen if the field of synchronous generator is removed when it is in operation with no load?
why tertiary winding is used in transformer with diagram?
what is difference between sub-station and switch yard.
can we amplify dc signals.how can it be done
what are the names of oil used in transformer and its chemical name?
What do you understand by avr?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)