If the maximum demand is 120 KVA in a building, then what is
the Current taken according to load given ? Formula for it ?

Answers were Sorted based on User's Feedback



If the maximum demand is 120 KVA in a building, then what is the Current taken according to load gi..

Answer / jose

120 kva means you have to supply 3 phase load.
3 phase load with 415 v and unity pf can take a current
according to eqn kva=1.732*Kv*I
I=120*1000/(415*1)=290 A appr

Is This Answer Correct ?    6 Yes 0 No

If the maximum demand is 120 KVA in a building, then what is the Current taken according to load gi..

Answer / basharat khan

a Generator of 1KVA can supply upto 1.4 amps, so the maximum load could be 1.4*120

Is This Answer Correct ?    2 Yes 1 No

If the maximum demand is 120 KVA in a building, then what is the Current taken according to load gi..

Answer / rajamanickam

KVA=V*I; KW=KVA*COS

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

why we use choke in tubelights nad other lighting fixer

1 Answers  


what is meant by excitation current & armature current ? where its produce & how we can calculate ?

0 Answers  


In a synchronous machine if the field axis is ahead of the armature field axis then the machine is ?

1 Answers  


In an ammeter used for measurement of current, what is the meaning of the representation of range as '0-50-300'?

4 Answers  


Why do we pefer VCB over OCB?What are the advantages of VCB over OCB?

0 Answers   CEB,






FULL FORM OF MCCB

3 Answers  


what is emitter follower configuration? and what are it's features?

1 Answers   IBM, TATA,


What is the basic difference between the electrical engineering and electronic engineering?

4 Answers  


please explain power factor in simple words.....

3 Answers  


The unit of resistivity is:(a) ohms(b) ohm millimetre(c) ohm metre(d) ohm/metre

4 Answers  


What is the difference between Welding Transformer and Normal Transformer?.

2 Answers   DAE,


What is multiplying factor of meter if the meter ctr and ptr is open type?

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16636)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)