What is the calculation for finding cement and sand for 10' * 12' area ratio 1:6 thickness 12 mm

Answers were Sorted based on User's Feedback



What is the calculation for finding cement and sand for 10' * 12' area ratio 1:6 thickness..

Answer / raghavan

0.019m3 of cement,0.12m3 of sand

Is This Answer Correct ?    0 Yes 0 No

What is the calculation for finding cement and sand for 10' * 12' area ratio 1:6 thickness..

Answer / nilesh kulkarni

Area
10 12 120 Sqft


Assume 100 Sqm of surface area for plastering
Thk = 0.015 X 100 = 1.5 Cum is the Qty of Plaster
Add 55% for (Bulkage,Uneven surface,Wastage etc)
1.5 X 55% = 0.825
Add It In 1.5 Cum 1.5 + 0.825 = 2.325 Cum is the Qty of Plaster
Ratio 1:6
So 2.325 Divideded (1+6) = 0.332 is the Constant For Material

Cement is 1 Part 1 X 0.332 = 0.143 Cum
Multiply By To Convert Into Bag = 28.8
No. Of Bags = 4.114 Bags Say 4.2 Bags For 100Sqm Surface Area

Sand 6 Part 6 X 0.332 = 0.857 Cum Say 0.85 Cum For 100Sqm Surface Area

0.47 Bags Cement For 120 Sqft Area

0.095 Cum Sand For 120 Sqft Area

Is This Answer Correct ?    0 Yes 1 No

What is the calculation for finding cement and sand for 10' * 12' area ratio 1:6 thickness..

Answer / anil

how calculate sand

Is This Answer Correct ?    3 Yes 5 No

Post New Answer

More Civil Engineering Interview Questions

what is the difference between GSB & WBM ?

1 Answers   CBC,


How many binding wire is use in arrangement of 25mt steel

2 Answers  


Is it worthwhile to carry out tests on particle density of soil particles for geotechnical design?

0 Answers  


As column is compression member then why we use steel to make it reinforced as it is already capable of taking compressive load?

2 Answers   MBL Infrastructures,


the magnitude of the buoyant force can be determine by newtons law of viscosity archimidies principal principles of momemnt none

0 Answers  






what will do when 7days concrete has failed and structure has constructed?

6 Answers   Modi Builders,


How to calculate concrete,s cement, sand, metal on the bases of its ratio. For any volume of work please give me brief calculation

5 Answers   L&T,


PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.

0 Answers  


Standard weighs for different grades of concrete?

5 Answers  


how to calcalate for roof beams & slab reinforcement design specified?

1 Answers  


what is the load capacity of bored pile pile dia 500mm

1 Answers  


what is the weight of 12mm aggregates?

0 Answers   Apache,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)