How to calculate productivity of construction equipment
like excavator, dozer, rock breaker, riper
Answer Posted / vinod k
I think 75% efficiency is correct as excavation of soil itself takes time & depends upon the area where excavation is to be done, if the excavation area is mix of soil & rocks then efficiency will be less & No. of cycles/hr will also come down.
This calculation is for ideal condition.
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
On what basis we decide the formation level of the road? other then that of 50% Cutting and 50% Filling??
Stringer How many cm goes to landind
what is mc arther pile?
What is the wall thickness of NP-3&NP-4 hume pipe as per I.S code
what is civil engineer greatest strength and weakness?
in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
What is the likely strength of a 1:2:4 concrete mix?
Is there the dry coefficient of cement is constant?
For fine aggregate which is most suitable River sand or crusher sand & why ?
what is civil enginnering & what you need of this course?
What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster
Define What is a projection line?
What is portland cement
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.