How to calculate productivity of construction equipment
like excavator, dozer, rock breaker, riper
Answer Posted / vinod k
I think 75% efficiency is correct as excavation of soil itself takes time & depends upon the area where excavation is to be done, if the excavation area is mix of soil & rocks then efficiency will be less & No. of cycles/hr will also come down.
This calculation is for ideal condition.
Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
I want to join bhel because
What difference comes in constructing of house and a housing complex like society
How much area will be covered in 1 litre of Velvet touch paint in normal wall condition
How to calculate volume of concrete & steel on tank foundation & ring wall ?
how many tonnes equals to one cubic feet?
Bitumen grades are 30-40,60-70, 80-100. what is mean by 30- 40
while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.
what is the ingredient value of 40mm and 20mm aggregates?
For Wet Mix Mecadam design what is Optimum moisture content
When column of building is abutting the boundary line,then suitable footing advised is
how to calculate the dry wt of sand and cement for a required design mix?for ex:M20
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
What is the difference between yeild strength and compressive strength of steel???
How to calculate concrete in percentage wise ,for example cement 18% sand 40% aggregate 40% and Stell 2% ,I need and??
what is SDLC ?and write a 'c'program for to swapping the three numbers?