Answer / shaikh moyunuddin
for rcc minimum M20 grade is used
it's depend how's the building is design
& m20 propotion is 1:1.5:3(cement:sand:aggregate)
& for water 40 to 55%
total area of rcc
| Is This Answer Correct ? | 26 Yes | 4 No |
Answer / sandip
the water cement ratio of m-20( 1 : 1 1/2 : 3 ) is taken normally 0.45 . Example for 1 cmt m-20 grade of concrete cement consumption is around 350 kg, thus the water consumption will be as below
consumption of water = cement x 0.45
= 380 x 0.45
= 171.00 kg ( =188 lit )
| Is This Answer Correct ? | 10 Yes | 4 No |
Answer / csr
It depends on which grade we are using and it depends on
the required strength.
minimum we start from M15 1:2:4,
M20 1:1.5:3,
M25 1:1:2
| Is This Answer Correct ? | 6 Yes | 3 No |
Answer / shri
m20 1:1.5:3 Cement:Fine aggregate:coarse aggregate water in ratio 0.5
| Is This Answer Correct ? | 3 Yes | 7 No |
Answer / hiren
in rcc generally M-20 is used hence for M-20 proportion are
1:1.5:3.... c:ca:water
| Is This Answer Correct ? | 9 Yes | 16 No |
Answer / fathi abu sabha
for m20 1:3:6 , cement ,sand , aggregate
for m30 1:2:4 , cement ,sand , aggregate
| Is This Answer Correct ? | 8 Yes | 17 No |
in staad pro. modelling for a parallel scissors chord truss, when i assigned roller support i.e fixwd but with all Fx, FZ, Mx, My and Mz release except Fy... the analysis results " in stability at a joint, with direction Mx or My..what could be the reason...anyone please explaing
percentage of metal,clay or soil & water in water bond macadam roads to know the quantities for each in total volume of 11500 cubic meters
howto calculate the quantities of material used in fly ash brick after finding the volume??
sir i have 2700sq.ft area.i wish to make a coomercial space including this area.sir what could be the estimated cost of 3 story bulding in varanasi.
How much overlapping required for welding the reinforcement bars in Columns & beams
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
How do you to separate Marble and Granite. What are difference between them?
Does vetrified tiles needs to be cure before fixing?
how much time will take for G+22 building for completion? activity wise like excavation,sub structure,superstructure,finishing,handover?
LET ME KNOW HOW IS CALCULATE RUBBLE WALL .3'00" IN BOTTOM 1' 6" IN TOP HEIGHT 8' 0" AVERAGE. length 200'00". please give correct answer.
what will be the quantity of following materials in P.C.C for the total area of (100'x70'x 0'4") 1)NO. OF CEMENT BAGS 2)SAND IN CU.FT 3)METTLE IN CU.FT
0 Answers Pratibha Industries,
What is the soil bearing capacity ? And how it should be to built a multistory building ?
3 Answers Clancy Networks, eConstruct, UltraTech,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)