How to calculate material and labor required for 100 m2 plaster?



How to calculate material and labor required for 100 m2 plaster?..

Answer / Pushpender Singh

For 100 m² plastering, you will need:
- Cement Plaster: 8-9 bags (assuming 25 kg per bag)
- Sand: Approximately 30-36 cubic meters (assuming a 7:1 cement to sand ratio)
- Water: About 400 liters (depending on the mix consistency)
Regarding labor, the number of masons needed and the duration would depend on various factors like work efficiency, team size, etc. A general estimate could be 2-3 masons working for 5-7 days.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

1m3 of brick is equal to how many cft of brick

9 Answers   DG Khan Cement,


What is difference between MS and Tor steel ?? Please ellobrate...or state its charactersitcs??

4 Answers   CLG, Indiabulls, TOR,


How to repair the Pavement quality conc used for toll plazas if is giving hungry look or honeycombed ? how much cement need to treat 100sqmtr of Damaged PQC

2 Answers  


Can anyone tell me the salary and job profile of transportation engineers/transport engineer?

1 Answers  


why seismic analysis not done during design of slabs

3 Answers  


16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.

1 Answers  


What are the different grades of concrete ?

3 Answers  


Give list of building construction equipment & explain about them in brief. How much is fuel consumption of JCB, DUMPER, POCLAIN, TRANSIT MIXER?

2 Answers  


The slenderness ratio of a column is zero when its length ??

2 Answers   SSC,


How to provide spacer bar in barbending work,parallel to bar or inclined to bar? What is the reason?

4 Answers  


why canot DBM is continue as surface coarse insted of BC? what is dieefrence between DBM & BC?

1 Answers  


how to determine the correctness of proportion used in cement mortor and various IS codes to determine the same?

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)