what is the real de-shuttering time for rcc column,slaband
wall
Answer Posted / shishir bhansali
rcc column 12 hours
rcc slab depending upon the span. from 5 days to 14 days
rcc wall 12 hours
| Is This Answer Correct ? | 29 Yes | 3 No |
Post New Answer View All Answers
How foundation is designed, Column design and beam design
how do you calaculate the total steel quantity of an rcc building using thumb rule?
Which code is used for tor & tmt steel bar?
What is the material consumption- cement,sand,tiles etc for Toilet dado?
how i can calculate the actual nos & size of steel to make 1000sqft. x 3"thick slab
what is column foundation
i want texture painting pwd data
How much of the strength of concrete comes from post- production curing?
in a corner footing of a building, column lies in one corner. in this condition i want to know if the reactive pressure of soil will be uniformly distributed throughout the footing or will be uniformly varying as in the case of eccentrical loading.
What are segregation and bleeding?
what is the type of earthing
Does brick grows bigger every year?
what is directivity effect?
How can we make a hole in a solid rectangle using solidsworks?
rate analysis for cement pointing 1:4 , for 100 sq m