what is the real de-shuttering time for rcc column,slaband
wall
Answer Posted / royalcivil
the de-shuttering time for the slab is 21 days must.
for the column it should be minimum of 1 week
| Is This Answer Correct ? | 10 Yes | 26 No |
Post New Answer View All Answers
psc girder detail
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?
What is the mix propotion of M10,M15,M20,M25,M30,M40,M50.M60 cement content,aggrigate,sand and water ratio.
please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.
What is the Roll of Water Bonding under VDF road?
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
HOE TO YOU PLAN TO ACCHIEVE THE GOALS?
how to calculate valuation for the old building?
What is the significance of cost estimate knowledge for an architect?
What is the yield of 100 litres of water and 10 kg of cement in grout mix?
pls tell me , what is the water content
Material calculation of cm 1:6 for 1sqm
i have four storeyed rcc building.basement of the building is around 34 years old.it does not have pillar support.it is having lintel steel support at every 7 feet of construction. how long this building will lost long . can any body help me in this regard
While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?
What is the purpose of the gap in the road on this bridge?