What are the Noms/8hr for Concrete Work for Mason,Carpenter,Steel Fixer
Answers were Sorted based on User's Feedback
RCC - 3CUM (125CFT) PER MASON
SHUTTERING - 9.6sqm
REINFORCEMENT- 1 quintal
Is This Answer Correct ? | 9 Yes | 1 No |
Answer / syed muhsin.s
As per ISO Norms
For Concreting = 1.5cum/8hr
for shuttering (carpenter) = 4 Sqm
for Reinforcement (Barbender) = 100 Kg..
Is This Answer Correct ? | 1 Yes | 5 No |
How can calculate cement quantity in brick work
what is development length,where it is used and why it is used?
Name four load bearing elements (structural elements) in a framed building
what would be the rqmnt. of cement and sand (1:6)for building brick wall and also 20mm thick plaster on the wall by same ratio?
Define What are the reasons for geotechnical site investigations in Uganda?
How do you calculate the mix ratio of concrete i.e. what is the cement:sand:agrugate ratio in 20Mpa, 21Mpa, 22Mpa etc...
how can calculate cutting length of diamond ring
how much used soil in 1 brick of standard size?
0 Answers Global Career Solutions,
How to find the weight of steel in feet? e.g: dia of steel is (6"') sut. We know that (1" inch 8 sut).
What are the Tests required to check the Quality of bar?
what"s the ratio for M30,M35,M40,M80 grade concrete?
Concrete Mix designs for M15,M20,M25,M30 and M35
23 Answers Arelgee Consultants, ATCO, Fusion, Gammon, Power Cable, Raushan Engineers, Simplex,