What are the Noms/8hr for Concrete Work for Mason,Carpenter,Steel Fixer
Answer Posted / syed muhsin.s
As per ISO Norms
For Concreting = 1.5cum/8hr
for shuttering (carpenter) = 4 Sqm
for Reinforcement (Barbender) = 100 Kg..
Is This Answer Correct ? | 1 Yes | 5 No |
Post New Answer View All Answers
What are the responsibilities of a site manager?
What are the reasons for geotechnical site investigations in uganda?
Why M15 is replaced by M20 when ammendment are made in IS456 in 2000?
Find out Cutting Length of Steel for Right angle Triangle? Where Opposite Side 4m, Adjacent side 6m. (Assume cover 40mm)
i need the syllabus for the direcr recruitement of executive engineers in andhrapradesh
how to calculate the chair reinforcement length in slabs, footing or anywhere??
What are the techniques to measure road difference?
Discuss some applications of modular elasticity?
I want to know the material required per Square foot in rcc roof i.e.Steel ,Cement,
insted of bentonite we can use any alternate material in piling ?
What is a hatch patterns?
when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?
How much is the cover for slab?
what discoveries did you have in relation to your course?
what is SDLC ?and write a 'c'program for to swapping the three numbers?