a) we have 30nos., 300mm dia, 4m length double under
reamed piles.calculate excavation quantity.b) tell
concrete qty. also.
Answer / bharath m
Hai,
Please find the answers below.
a)Excavation quantity
Straight pile = 3.14/4*.3*.3*4*30 = 8.49 Cum. +
Under reamed portion (2 Nos. per pile) = 2*3.14*.318*(.2)*.225*2*30 = 5.39 Cum. Total = 8.49+5.39 = 13.88 Cum.
b)Concrete quantity
as same as item (a) above.
Bharath M
Tamil Nadu
8438238335/9980644165
| Is This Answer Correct ? | 3 Yes | 7 No |
which formula used for calculate the area of segmental arch?
Which ratio use for cement selery???
How do You Maintain a structure after getting cube test of low strength.
What is the standard rate of installing ties for column(60cmx60cm) and beams(50x850)(weight)
why wire mesh is used in plastering
HOW MANY CEMENT BAGS ARE REQUIRED FOR 1m^2 PLASTERING AREA?
Whats maxi. slump of M-7.5 Concreit for PCC
2 Answers Indiabulls, Swastik Group,
What things architect have to take care of before starting any project?
in the construction of building,we are use formula for laping? such that how many formulae we use? which are them?
HOW MANY CEMENT BAGS ARE REQUIRED IN 1 CUBIC METER
11 Answers Bharat Construction, CPWD, Ircon,
What is the formula to calculate the volume of mortar required for a wall with 1245 blocks with a stndard size of 440x215x100?
Which types of Water Proofing to Be used in Swimming Pool.
2 Answers CCEL, Ideal Construction,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)