a) we have 30nos., 300mm dia, 4m length double under
reamed piles.calculate excavation quantity.b) tell
concrete qty. also.
Answer Posted / bharath m
Hai,
Please find the answers below.
a)Excavation quantity
Straight pile = 3.14/4*.3*.3*4*30 = 8.49 Cum. +
Under reamed portion (2 Nos. per pile) = 2*3.14*.318*(.2)*.225*2*30 = 5.39 Cum. Total = 8.49+5.39 = 13.88 Cum.
b)Concrete quantity
as same as item (a) above.
Bharath M
Tamil Nadu
8438238335/9980644165
| Is This Answer Correct ? | 3 Yes | 7 No |
Post New Answer View All Answers
how much concrete solid/hollow block are manufacture per 50 kg cement bag in differnent sizes like 400x200x200mm, 400x200x150mm, 400x200x100mm. And need proper ratio as per sale quantity. pls send my mail mathi7599@gmail.com searching last two years not yet get pls find and enclosed pls. need practical analysis.
Define What is the difference between routing maintenance and major maintenance in school facilities?
How we can calculate the cement, sand,bricks , water , quintity in 1:6 Ratio 1 cubic metre b/w and 1:4 Ratio in 1 Squre metre b/w????
what is civil all interview questions
What is the thickness of slab for 600 sq each) 2 slab construction. What should be the size of steel rod?
how can can column be corrected when the design is not safe ? is the increasing the clearcover a solution?
What do you mean by tolerance factor of concrete ?
what are the duties of Site Engineer in work site?
all technical question
150mm bricks size how many use 4.14 m3
The portion of a brick cut across the width is called?
what is detail procedure of eccentric footing? plz. give solved exmple?
How can i display 5 asterisk and another 5 asterisk )?
sir please send me campus placement questions in civil engineering
Why are steel plates inserted inside bearings in elastomeric bearings?