a) we have 30nos., 300mm dia, 4m length double under
reamed piles.calculate excavation quantity.b) tell
concrete qty. also.
Answer Posted / bharath m
Hai,
Please find the answers below.
a)Excavation quantity
Straight pile = 3.14/4*.3*.3*4*30 = 8.49 Cum. +
Under reamed portion (2 Nos. per pile) = 2*3.14*.318*(.2)*.225*2*30 = 5.39 Cum. Total = 8.49+5.39 = 13.88 Cum.
b)Concrete quantity
as same as item (a) above.
Bharath M
Tamil Nadu
8438238335/9980644165
| Is This Answer Correct ? | 3 Yes | 7 No |
Post New Answer View All Answers
how to calculate freeboard in under ground water tank and technical details
Explain the different types of building contracts?
How to fix toll charge for a particular vehicle at toll booths in a highway?
psc girder detail
Bernaullis theorem deals with the law of conservation of mass momentum energy none
how much cement sand n bricks required in im3?and how much in plaster?
The internal dimensions of a wire house 15m*5.6m and the maximum height of piles is 2.70m. What is the maximum number of bags to be stored in two piles ?
foundation details for 25 ton weight Furnace on 2 supports and 2 tilters
Define graphics window?
construction workers how much time take one work or qty
Maximum cement content in 1cum for RCC and PSC? (please give IS,IRC referance?
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
how clculate excavated or backfilling quantity by simpson's rule
what is education Cess.
i have four storeyed rcc building.basement of the building is around 34 years old.it does not have pillar support.it is having lintel steel support at every 7 feet of construction. how long this building will lost long . can any body help me in this regard