Answer / thiraviam
after casting the salb it will take 28 days to cure
in 7 days time it will cure 65% and the rest will take
remaing days to cure
| Is This Answer Correct ? | 5 Yes | 1 No |
Answer / satishkumar
after 21 days.if ponding is not then 28 days curing reqd it may depends upon season.
| Is This Answer Correct ? | 1 Yes | 1 No |
Answer / manjunatha.h.s
How many days after the casting of a slab another slab can
be casted above it?
what is the total curing time of a slab if ponding is not
done on it?
As per codal provision 7days curing by ponding +7 days
continues sprinking should be done, Minimum of 14 days
curing should be done to start casting a new slab upon it
therewhich Back propping should be given to the lower slab
in the column capital portions,
In case if ponding is not done, continues water sprinking
should be done for 21 days
| Is This Answer Correct ? | 1 Yes | 1 No |
1m3 3/4 inch course agreegate concrete is which m3 of agreegate ?
what is the concrete mix design ratio of railway sleeper??????
How and where from do we get 162 for calculating sectional weight of TMT
what is the crushing strength of good building stone
What are the tests to be conducted on cement?
Hi Dudes, I have completed B.E Civil with two years experience in Highway& Bridges. One year experience in Site field & One year experience in Planning & Billing Dept. I am willing to work in abroad, i am having passport and all..So if anybody knows about foreign vacancy pls inform me..Ph:9994050979 & Mail Id: Simacivil1988@gmail.com
how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?
0 Answers NCC, Sobha Developers,
how the calculation occurs if i want to mix 1cum of M50 concrete. please calculate every ingredients with detail calculation.
what is PEB structure
calculate the cost for AAC block wall of 15cum?
Two types of piling
Number of cement bags required for concreting 1000 square Feet slab of 4 inch thickness.
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)