what is the stripping time of beam?
Answers were Sorted based on User's Feedback
As per Indian Standards:
1. Vertical form work to Beams = 16 to 24 hours
2. Props to beams Spaning up to 6.00m = 14days
3. Props to beams Spaning up to 6.00m = 21days
4. Props to be refixed immediately after
removal of form work = 7days
Is This Answer Correct ? | 11 Yes | 2 No |
Answer / yisahak
Generally form-work shall be stripped off after the concrete has attained 50% of the 28 day cubic strength, or when it attain twice the stress it will then be subjected after the removal of the form-work, which ever is greater.
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / sourish
Stripline is a beam diagnostics device used to measure beam
position/phase in particle accelerators.
Is This Answer Correct ? | 1 Yes | 3 No |
why we can use dust in concrete insted of fly ash
wha is frog?
how many kilogramme of sand comes in 1 brass ?
11 Answers Hindalco, Nikhil Construction,
What is the rate of earthwork excavation?
1)What is the maximum size of aggregate that can be used for M-50 grade concrete ? Code teh authority?
What is cementation
How to take steel quantity for beams ?how to calculate stirrups
How to calculate Volume of Wet cement concrete for a specific grade?
Deduction in length of reinforcement steel for bar bending
how calculate the bearing from two coordinates?
0 Answers DPTL, HPPCL Himachal Pradesh Power Corporation Limited,
How many mortar required for Brickwork of 1 Cu.m works??
how to calculate no. of cement bags consumed in 1:4 and 1:6 proportion RR Masonary and the quantity of sand also