Answer Posted / jai.vignesh
As per Indian Standards:
1. Vertical form work to Beams = 16 to 24 hours
2. Props to beams Spaning up to 6.00m = 14days
3. Props to beams Spaning up to 6.00m = 21days
4. Props to be refixed immediately after
removal of form work = 7days
| Is This Answer Correct ? | 11 Yes | 2 No |
Post New Answer View All Answers
In block work seawalls what is the purpose of slip joints?
undistributed samples are obtained by
what mean By core Billing
what is constat for brickwork
how many running meters in one kilogram of 4mm pvc coated chainlink fencing
The largest size of paper used in plotter to print the drawing made by Autocad .
what will be density of a cement bag if its weight and volume are 50kg and 1.25 cft respectively???????
Mention what are the composition of a landfill?
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
WHAT IS THE CAUSES OF RUTTING ON FLEXIBLE PAVEMENT?
How to calculate 1 brss for RCC work
How much material is required for constructing a 2 Lane 2Km rigid pavement road
I want to change job.If You have any vacancy please contact me in this mail id-parthamitra086@gmail.com.Myself partha mitra.Diploma in civil engineer with 4+ yrs. exp.Now in kolkata.If you confirm me then I will send my detail resume to you.Also send your mail id to me.My mail id is-parthamitra086@gmail.com.I will be very much thankful to you.
how do we calculate quantity of cement sand and aggregates in 1m3 of m20 m25 grade concrete?
when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?