Answer Posted / yisahak
Generally form-work shall be stripped off after the concrete has attained 50% of the 28 day cubic strength, or when it attain twice the stress it will then be subjected after the removal of the form-work, which ever is greater.
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?
A super elevation of 60 cm has been provided on a 8m wide road and a curve of 260m radius .calculate the max.speed in km/hr of the vehicle that can be negotiated safely? Plz answer with full solution.thanx
if dia of inner circle is 42 m and depth is 1.5 m and width is 1 m ,then whait is the quantity of steel?
what is the use if we fixed butterfly ties in column and masonry work joint?....where we have to fix(distance)..
Civil engineering related
What is the strength of 1:6:12 mix?
What is meant by solid geometry?
what is meant by csr in foundation? what is sbc?what is meant by contour line?
can stub column take the load as main column
How to find the cuplock pipe qty in staging for Minor bridge?
What are the different types of foundation?
pls mail some more tecnical qustions at msaranya2610@gmail.com
Need help in designing a degasser tower for 2m3/hr DM plant, also send me the formulae used
for 32 dia (EQR HYSD steel) bar how much deduction for 45 and 90 degree band
Spider cracks occur in beam bottom due to––