what is the cover used for footings, columns, beams ??? why
they differ & how they arrive??




Answers were Sorted based on User's Feedback



what is the cover used for footings, columns, beams ??? why they differ & how they arrive??..

Answer / prakash

For Footing 50mm
Column 40mm
beam 25mm
slab 15mm

They arrieved as exposure condition.

Is This Answer Correct ?    43 Yes 4 No

what is the cover used for footings, columns, beams ??? why they differ & how they arrive??..

Answer / dinesh koli

Footing/raft side-75mm top & bottom-50mm
Colmn below gr.level-65mm
Column above gr.level-40mm
Plinth beam top, bottom, side-50mm
floor beam top-25mm, bottom-40mm, side beam>150mm-40mm beam <150mm-25mm
floor slab top & bottom-20mm

Is This Answer Correct ?    4 Yes 1 No

what is the cover used for footings, columns, beams ??? why they differ & how they arrive??..

Answer / sreenivas chitrala

For Footing 50mm
Column 40mm
Beam 20mm
Slab 15mm

Is This Answer Correct ?    5 Yes 3 No




what is the cover used for footings, columns, beams ??? why they differ & how they arrive??..

Answer / bala

According to Nominal cover as per IS 456:2000 The Exposure
condition matters,
For condition
Mild - 20mm
Moderate - 30mm
severe - 45mm
very severe- 50mm
& Extreme - 75mm

so for
Footing - 75mm
Column& Beam - 45mm

Is This Answer Correct ?    10 Yes 10 No

Post New Answer



More Civil Engineering Interview Questions

i want to ecil (Electronics Corporation of India Limited Hyderabad) previous civil engineering question papers immediately please.............

0 Answers   Ecil,


what is a steel formula

13 Answers  


what is concrete

9 Answers  


A beam having top bars 20dia,bottom bars 16 dia.is the design is ok? In which case this applicable?

6 Answers  


When brick size is 3x5x9" , what would be the number of Brick requirement for 100 sqft area of 5" width?

5 Answers  






Define What is the meaning of a blue land surveyors flag?

0 Answers  


Why should you show Client/Engineer activities clearly on the project plan?

0 Answers  


Which construction joint is much better ? either vertical or horizontal?

2 Answers   Pratibha Industries, MNT,


what is levelling staff least count

13 Answers   L&T,


what is the quantity of cement( in bags),sand and aggregates required for 1 cmt of M 25 concrete

3 Answers  


Should vertical shuttering done for CC/ RCC for Damp Proof Course (DPC) be measured?

2 Answers  


How can we find out the clear cover for a circular ring and rectangular ring..

1 Answers  






Categories
  • Civil Engineering Interview Questions Civil Engineering (5068)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4436)
  • Electrical Engineering Interview Questions Electrical Engineering (16570)
  • Electronics Communications Interview Questions Electronics Communications (3914)
  • Chemical Engineering Interview Questions Chemical Engineering (1091)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (214)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (258)
  • Instrumentation Interview Questions Instrumentation (2983)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (96)
  • Marine Engineering Interview Questions Marine Engineering (122)
  • Power Plant Engineering Interview Questions Power Plant Engineering (170)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (0)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1376)