for 100sft of Cement plastering ratio 1:6 How much quantity
of cement and sand required.
Answers were Sorted based on User's Feedback
Answer / ketan khetia
pls give detail that what is the thickness 6mm 12mm or 20mm
its depends on that
For 6 mm plaster cement use will be 0.25kg/sq.ft
for 12 mm plaster cement use will be 0.5kg/sq.ft
for 20 mm plaster cement use will be 1.0kg/sq.ft
Is This Answer Correct ? | 111 Yes | 17 No |
Answer / ahmed jaleel if any clarifica
100/3.28^2=9.29
1:6
The theekness of Plastering is 12mm
Sand is Requried in 1 cubic Mtr =1.25
Cement Is Requried In 1 cubic Mtr 1.25/6= .21
9.29 * .012 = .11148 * 0.21 =
.023 * 1440 = 33.71 Kgs Is Cement Requried.
( With Out Westage )
Sand = 1.25 * .023 = .02875 Cubic Mtr Sand Requried. ( With Out Westage )
Is This Answer Correct ? | 60 Yes | 16 No |
Answer / mohammed aijaz hussain
Let the thickness of Plastering be 12 mm.
Volume of Wet Mortar = 12mm X 100 sft.
= 12/ 1000 X 100/ 10.76
= 0.112 cu.m.
Add 20% for depressions, joints and wastage:
= 0.022 + 0112 = 0.134 cu.m.
Volume of Dry Mortar = 1.3 X 0.134 = 0.175 cu.m.
Cement required = 1/7 X 0.175 = 0.025 cu.m. = 0.71 Bag
Sand required = 6/7 X 0.175 = 0.15 cu.m.
Is This Answer Correct ? | 41 Yes | 21 No |
as per west baengal sor
10mm plaster 0.2cum cement and 1.2cum sand
15mm plaster 0.3cum cement and 1.8cum sand
20mm plaster 0.4cum cement and 2.4cum sand
Is This Answer Correct ? | 22 Yes | 16 No |
Answer / ashraf aslam
unit of rates=100 sft thickness of plaster let 1 inch wet volume of mortar=100*1/12=8.33 cft dry volume of mortar=8.33*1.27=10.58 cft {1.27 azafa dry vlm } ratio=1:6 sum of ratio=1+6=7 qnty of cmnt=1/6*10.58=1.76 cft or 1.76/1.25=1.41 bags qnty of snd=6/7*1o.58=9.068 cft
Is This Answer Correct ? | 11 Yes | 8 No |
when it is noted "JAMB SIM" what is the term "SIM" and what does it mean?
how to calculate the 45 degree bent up length. if we given that whether the total length of the slab reinforcement will increase or not. mantion it clearly please. this is for bar bending schedule purpose?
WHAT SHOULD BE THE THICKNESS OF CEMENT M-SAND MIXER IN BETWEEN TWO SOLID CEMENT BRICKS USED FOR A HOUSE WALL?
Sir I am from jntuk R13 regulation...... Is there any chance to leave credits
10'0" × 10'0" Proposed room Start and Finish How many Cement & Sand & Bricks & Metals & Steels Need
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
What are the skills required to become an architect?
What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?
How to rectify thermal cracks (2mm wide, 9mm deep aprx. ) developed in tremix finished concrete floor?
how many cement bags rquired for solid block construction for 100 sqft in 1:6 proportion?
a) Difference between Ghol , Chimney & fly ash bricks b)Floor to floor height is 3m , rise=15cm , tread 20 cm , how to design staircase means steps landing
what bending moment?