for 100sft of Cement plastering ratio 1:6 How much quantity
of cement and sand required.
Answer Posted / vishal singh
12mm plaster 1 beg of cement & 7 cft sand
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
Explain the water bound macadam roag
What is quantity of cement and sand required for 2000sqft of tiling?
can i get hindi version of is codes based on civil engineering?
What sizes of stones chips are used for foundation, column and floor casting. Please answer in detail.
suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?
Explain what is Hybrid Foundation?
What do you mean by tolerance factor of concrete ?
What is the force exerted by the tacoma narrows bridge?
how to stop beam concrete between column
how do we design mix ratio?
how clculate excavated or backfilling quantity by simpson's rule
How you read 5x3x1 #4 @ 20" 0/C in steel structure?
how to take concrete quantity for precast segment for viaduct project?
how much cement and sand consuptin in 4 inch siporex walls 100 sq ft
how many type of admixtures for water stored structure?