how to syncronize two dg sets
Answers were Sorted based on User's Feedback
Answer / k.kadiresan
For Synchronizing two DG sets, the following parameters to
be checked.
1. Voltage rating of the DG sets and voltage before
paralleling of both DG sets should be equal.
2. Both DG sets Frequency to be checked and should be equal.
3. The Third parameter is the Rating of the DG sets. It
shall be equal. If there is any difference, the percentage
of loading will differ.
4. After paralleling to maintain equal loads, the frequency
to be adjusted.
Is This Answer Correct ? | 3 Yes | 1 No |
Answer / arvind
all r correct parameters but one is not mentioned as polarity polarity of both d.g should be same or the alternators will burnt out they donot bunt recently as reverse diodes r placed between them they get first burnt if they not then alternator will get burnt
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / raghu
Need to be match voltage, PF,is same at the both the dg.
Is This Answer Correct ? | 2 Yes | 3 No |
how does electrical train works and what type of motors are used to drive the train? which level of supply voltage is used?
Dg pf .71 i am improve pf 0.80 what capacitor connected in dg how?
0 Answers AVT Natural Products, EMC,
i installed 100kva ups. what KVA genset they should provid in input side? plz any update formula or ans with reason.
What is the alternate solution for testing of polarity by using polarity tester while its milli ammeter does not works?
Rotor is taken away from three phase induction motor and three phase supply is given to the stator.What will happen?
what is recommended breakdown voltage of transformer oil?
what is appearent power?
There is one 40MVA oil cooled transformer (yet to commission), filled with 95% oil and we are trying to fill 5% Nytrogen in that transformer so that there should not be any foreign component inside. But even though there is no leakage, nytrogen is not withstanding inside transformer, within a day or two pressure guage is showing 0. Why is it soooo? Pls reply.
Hai, I am from EEE branch.On feb 17 iam going to write an Exam for hindustan petrolium corporation Ltd.So plz send me the written exam pattern/Q's/interview questions.please mail to yuva_polisetti@yahoo.co.in
What are the limiting factor for controlling maximum hot point temperature within a hydrogen and water cooled generator?
how many stairs have you climbed while you were coming
What is the importance of counter based plan & how is it scheduled?