While testing the 33KV Busbar by using Hipot kit, what
should be the test
voltage we have to apply?
Answers were Sorted based on User's Feedback
Answer / dharmaraj
you apply voltage 80% factory testing.......
if example factory testing 70kv means
you apply 70*0.8 = 56kv. for 33kv busbar........
Is This Answer Correct ? | 4 Yes | 2 No |
why dc series moter is not started at no load?
To transmit the Power which must be present…? a) Reactance b) Resistance c) Capacitance d) none of above
delta motor winding resistance I take normally single winding is 2.5, which value is came delta connection ie RY ?
what is power factor for any engineering equipment?? what should be its value?
what are the industrail measures to over ferranti effect? how would the ferranti effect the power system if those remedial mearsure arent taken? how often does this effect occurs in real power system?
wat do knw aboot circuit breakers ?
as ac supply is given 2 the transformer why it doesnot depends upon powerfactor????
what is meant by differential protection of transformer
How to connect frequency meter in metering circuit?(single phase and three phase frequency meter)
For 280kw power. Which cable I can usr
sir pls send the je exam - 2008 and other model question papers..
what is acceptable leakage current for 33kv cable while doing high voltage test for cable? how to calaulate the leakage current for 33kv or any rated cable?