how clculate excavated or backfilling quantity by simpson's rule

Jaypee,

3813

What is "Bending moment"? Demonstrate on theory not for formula.

3 5172

How to calculate the crank length of the rod in beam? Please give me a details.

Agarwal Associates,

3 19904




How Calculate Lap Length

L&T,

10 37011

why we do pcc.?

6 6061

door and window wood work calculations and different methods

APPSC,

847

binding wire requirement in rcc structures

6 8203

give the full form for upvc pipe & cpvc pipe

ME, PVC, SWR,

4 68351




What is the basis of choice for cement sand plaster in ratio 1:4 and 1:6 on interior walls of a residential apartment.

Gammon,

3 14913

what is a well

696

if rise and tread of stairs rae 16 & 25cm with landing slab of thickness 100mm . If there are 8steps, and carpenter ask for to mark the bottom of centering of landing on column, what will be the height above floor finished level?

2 3198

how many labour is required for 1cum of concrete?

6 17569

plz answer the questions, How do you check the quality of foundation? and What is the key performance area in quantity survey?

1 2911

how many kilograme per metre run of 6mm diameter steel bar

6 4752

how can change 12mmdia@150c/c bar spacing to 16mmdia

Envoy Group, Globus Constructions, Amanah Tech,

12 78500


Post New Civil Engineering Questions






Un-Answered Questions { Civil Engineering }

Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required

567


can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.

760


I need model question papers for writing the Dubai municipality exam,for G+1

227


What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?

1394


What is geopolymer based concrete?

1030






While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?

193


What is portland cement

5204


At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.

830


contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?

934


a) Difference between Ghol , Chimney & fly ash bricks b)Floor to floor height is 3m , rise=15cm , tread 20 cm , how to design staircase means steps landing

1706


Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.

1344


How to calculate ventonite bag in pile ( pile depth 25 m dia 1m)

173


what is c4x light weight cement blocks

4021


5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)

742


How will you reduce the concrete flow after mixing the concrete

867