Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what is right time of slab DE shattering and beam boo tam.

Answers were Sorted based on User's Feedback



what is right time of slab DE shattering and beam boo tam...

Answer / map

It depends up on span of the beam normally after 7 days we can remove shuttering and support with props.

Is This Answer Correct ?    24 Yes 4 No

what is right time of slab DE shattering and beam boo tam...

Answer / azam

The time of slab deshutting after getting 67% strength at 4 or 7 days same for beam bottom and it also depend of span of beam.

Is This Answer Correct ?    21 Yes 3 No

what is right time of slab DE shattering and beam boo tam...

Answer / ronak shah

as per IS 456 beam bottome should be remove after 14 days.
concrete strength is more than 70%. if span is more than 11
mt then its remove after 21 days.

Is This Answer Correct ?    12 Yes 1 No

what is right time of slab DE shattering and beam boo tam...

Answer / sahilshah.civil@gmail.com

As per IS 456:2000

a) Columns/vertical member : 16-24 hrs
b) Slab - 3 day - prop to be kept below
c) Beam - 7 day - prop to be kept below

props to slab
a) spanning up to 4.5 m = 7 day
b) spanning over 4.5 m = 14 day

props to beam
a) spanning up to 6 m = 14 days
b) spanning over 6 m = 21 day

Is This Answer Correct ?    3 Yes 0 No

what is right time of slab DE shattering and beam boo tam...

Answer / mitesh patel

Beam Sides can be allowed to be removed on the next day of
casting.
Bottoms should be allowed only after 7 days of casting.
This is practical answer on site otherwise contractors will
run away.

Is This Answer Correct ?    1 Yes 0 No

what is right time of slab DE shattering and beam boo tam...

Answer / ananth

span length below 4.5m 7 days
span length over 4.5m 14days

Is This Answer Correct ?    1 Yes 0 No

what is right time of slab DE shattering and beam boo tam...

Answer / md nezam

DE shattering can be done for slab bottom after 3days and Beam bottom after 7 day,but immediately props to be refixed.

Is This Answer Correct ?    3 Yes 3 No

what is right time of slab DE shattering and beam boo tam...

Answer / sagar tiwari

span length over 6m than 28 days
span length below 6m than 14 days

span length over 4.5m than 14 days
span length below 4.5m than 7 days

Is This Answer Correct ?    0 Yes 0 No

what is right time of slab DE shattering and beam boo tam...

Answer / vinaysagar donakanty

The above answer were right but it is advisable to check strength of cubes at 3 days or 7 days or 14 days before deshuttering.

Is This Answer Correct ?    0 Yes 0 No

what is right time of slab DE shattering and beam boo tam...

Answer / r.ranjith kumar

slab de shetting 2 day

Is This Answer Correct ?    0 Yes 3 No

Post New Answer

More Civil Engineering Interview Questions

how much cement,sand,aggregate will use for 1 cum in ratio of 1:2:4.

16 Answers   ARS, College School Exams Tests, Gulf Construction, HRL, mWorkspace, NCC, URC Construction,


which is cover of r.c.c. column,beam and slab

5 Answers   Cube, RPP,


1 cft of brickwork 1:6 mortar ratio need 12 numbers of bricks so find the quantity of sand and number of cement bags

2 Answers  


Can compresive strength test for concrete at 1 day age possible to carry out? If yes, which IS code describes the procedure for such testing?

0 Answers  


difference b/w stress and strength

3 Answers   BMS,


IS sobha developers ,bangalore an good place to work for the freshers

5 Answers  


How to calculate the cement and fine aggregate requirement for solid block masonry works in terms of Sqm. 1. 400x200x200mm 2. 400x200x100mm 3. 600x200x100mm 4. 600x200x200mm I need the answer for 1 Sqm of solid block works.

0 Answers   IVRCL, L&T,


What is the release of lien?

0 Answers  


what is diffence in grade 43 & 53 of cement?

4 Answers   KFC, L&T, NICE, Puravankara,


in the earthquqke the profile of water on dam is parabolic or not

0 Answers  


How many modular bricks are required for 1 cubic meter of brick masonry?

14 Answers   ITI, L&T,


What is the 162 in steel weight formula?

1 Answers   D H Patel,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)