how much cement,sand,aggregate will use for 1 cum in ratio of
1:2:4.
Answers were Sorted based on User's Feedback
Answer / lakshmanarajan
The Ratio is 1:2:4 Total = 7
Ingredients of this Mixture is = 1.57
So the qty of Cement is = (1/7) x 1.57 = 0.224 cum
Volume of cement in i cum = 1440kg
therefore required cement = 1440 x 0.224 = 322.56kg
Weight of 1 cement bag is = 50 kg
so 322.56/50 = 6.45Bag
Add 5% for wastage = 6.45 x (5/100) = 6.77 bag required
Qty of Sand = (2/7) x 1.57 = 0.448 cum (1cum = 35.31 cuft)
convert cum to cuft = 0.448*35.31 = 15.18 cuft
Sand is available in unit,so 1 unit = 100 cuft
So required qty of sand is = 15.18/100 = 0.151 unit require
Qty of Aggregate = (4/7) x 1.57 = 0.89cum
Convert cum to cuft = 0.89 * 35.31 = 31.42cuft
sand & Aggregate also available in unit
so above the same as aggregate = 31.42/100 = 0.314 unit require
| Is This Answer Correct ? | 85 Yes | 12 No |
Answer / roys
Ratio of concrete mix =1:2:4 (Calculation for 1cum)
Cement:-
1/7*1.54=.22 cum [1.54for dry volume]
=.22/0.0345
=6.38bags
Sand:-
2/7*.22=0.06cum
=0.06*35.32
=2.12cft
Aggregate:-
4/7*.22=0.13cum
=0.13*35.32
=4.59cft
| Is This Answer Correct ? | 61 Yes | 24 No |
Answer / mr. b.nagaraj
as per is 6.4 bags of cement & 0.86m3 / 30.31cft of 20mm
aggregate & 0.46m3 / 16.25cft of sand requires for 1m3 of
m15 concrete or 1:2:4
| Is This Answer Correct ? | 46 Yes | 21 No |
Answer / javed ashraf
6.22 BAG OF CEMENT IN ONE CUBIC METER
.44 CUM FINE AGGREGATES
.88 CUM COARSE AGGREGATES
| Is This Answer Correct ? | 25 Yes | 9 No |
Answer / prabakar
RCC 1:2:4 -density of cement=1440kg/m3 1m3 =1440/2=720*0.45
=324kg
=324/50=6.48bags
Sand=6.48*1.25
=8.0125cum
=2*8.0125
=16.025cum
Aggregate
=4*8.012
=32.05cum.
| Is This Answer Correct ? | 13 Yes | 3 No |
Answer / zeshan
Simply for 1 cum of ratio 1:2:4
Concrete 1 cum
Sand 1/2 cum
Cement 1/4 cum
| Is This Answer Correct ? | 8 Yes | 0 No |
Answer / er. syed layaq ali
practically Material Consumption in M15 1:2:4
Quantity-1 cum
Cement beg - 6 Nos(0.198 cum)
Coarse Sand - 0.396 Cum
Coarse Aggregate 0.792 Cum
| Is This Answer Correct ? | 7 Yes | 5 No |
Answer / n. rajesh guttedar
Materials used for a 1 cum.in the ratio 1:2:4.
Cement. = 6.336 Bags.or ( 0.220 cum. )
Sand. = 0.440 cum.
Aggregate.= 0.879 Cum.
| Is This Answer Correct ? | 7 Yes | 7 No |
What is the Null Point of chimney in Power Plant
What is the amount of brick in cum we get in a BIG LORRY approx ??
what is the actual productivity of carpentor,fitter,masson for brickwork and masson for plaster etc
Which type of plywood & sizes using in construction projects ?
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT
what is called camber in the road ?
what is tacheometry?
Slump Values for works?
0 Answers Aditya Constructions, SVS Constructions,
structural engineering based
a concrete mix 1 2 4 by volume with water cement ratio as .6 by weight if moisture content in F.A is 6% with 20% BULKING AND IN C.A 1.5% by volume. find quantities of different materials required for one bag of cement
difference between nominal mix and design mix difference between nominal size and actual size of brick,aggregate etc
VAT and CST ? Which benefits for buyer ? Why benefits?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)