what is right time of slab DE shattering and beam boo tam.
Answer Posted / azam
The time of slab deshutting after getting 67% strength at 4 or 7 days same for beam bottom and it also depend of span of beam.
Is This Answer Correct ? | 21 Yes | 3 No |
Post New Answer View All Answers
Why steel rods are produced only in even dimensions?
How do you calculate load bearing capacity of a waffle slab?
What is the diff between cad & cadd?
How to design staircase.plz tell me formula for the design the staircase.
material used for mendrel use to bend epoxy coated rebar
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
what is the procedure of wet seiving. n percentage of silt in different type of soil?
What is meaning of Canceled/Flat Beam. What is difference between them? Both type of beam can bear same load if size (width)of the flat beam is increases and depth is same as slab thickness? Kindly suggest to me.
Explain why concrete barriers have curved surface profiles?
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
What is the difference between 53 grade and 43 grade cement
A rock anchor 3 1/2” in diameter is placed in rock. The which has an allowable shear strength of 1200 psi. Determine the required anchorage length to safely carry a 80 ton load using a 2.0:1 F.S
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
Define aligned dimension?
what is the productivity in aluminium shuttering per day