what is right time of slab DE shattering and beam boo tam.
Answer Posted / sagar tiwari
span length over 6m than 28 days
span length below 6m than 14 days
span length over 4.5m than 14 days
span length below 4.5m than 7 days
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
for pretensioning which will yield first and same for post tensioning?
What is absolute coordinates?
What is the distance between railway tracks?
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet
how i convert mm into standard wire guage (SWG)no.
hi, i am doing my B.tech third year and i want to have a job in Genpact...So can you help me which kind of job would be more appropriate for me in such a company and How should i prepare for an interview?
indian standard split spoon sampler
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
TELL ME THE EQUATION FOR OGEE SPILLWAY
Which is the best book for building construction?
How to Rectify deep crack formed on Brick Wall? Explain the method of rectify the defect?
how much quantity of cement,sand and water required for 1 sq feet flooring work .
What are the phases inspections are done by local authority while construction?
satart to end steps by step process of building construction...? i want to planning theme accuretly
What is type failure of road surface? how to repair the failure of road surface?