what is the actual productivity of carpentor,fitter,masson
for brickwork and masson for plaster etc
Answers were Sorted based on User's Feedback
Answer / thiyaneshwaran shanmugam
1) 1 Carpenter + 1 Helper - 5.5 - 6.5 Sqm/Day
2) 1 Steel fitter + 1 Helper - 150 - 200 Kgs/Day (Cut, Bend, Placing)
3) 1 Maon + 1 Helper - 10 Sqm/Day (Blockwork)
4) 1 Mason + 1 Helper - 12 Sqm/Day(wall plastering)
5) 1 Mason + 1 Helper - 10 sqm/Day(Ceiling Plastering)
6) 1 Mason + 1 Helper - 8 Sqm/Day(External Plastering)
7) 1 Tiler + 1 Helper
12 Sqm/Day (Vitrified Tile)
10 Sqm/Day ( Ceramic floor Tile)
8 Sqm/Day ( Ceramic wall Tile)
Is This Answer Correct ? | 90 Yes | 3 No |
Answer / pradeep muley
1 fitter with 1 helper - 100 kg per day cutting, bending & placing,
Mason - 100 to 150 Sqft per day
Is This Answer Correct ? | 91 Yes | 23 No |
Answer / hari
1) 1m+1mh=10m2 blockwork per day
2)1m+1mh shuttering=around 5m2 per day
3)1m+1mh barbending=around 200kgs per day , inc cutting,bending,placing.
Is This Answer Correct ? | 11 Yes | 4 No |
Answer / n.v.ramana
1)CARPENTER=150SQFT.
2)FITTER=250KG/DAY
3)MASON=300BRICKS OR 1CUM
4)MASON-PLASTER=200SQ.FT/DAY.
Is This Answer Correct ? | 32 Yes | 51 No |
what type of cement are used for fixing of tiles at floor/wall
how many liters of water required for 1cu.m concrete?
Explain what is change order request?
hi guys what happens if you are absent for a supplymentry exam?
How much 1sqft area reinforce formula properly define
what is the name of shuttering oil used in oman
Dear Friends am S.PRABHU looking for job chnage i have wonderfull exposure to both Construction works & i have a experience 11 years if any found any suitable opening, please Contact 9986539249
how to calculate the material from ratio of work PCC, RRM,POINTING, RCC
How many types bend used in civil reinforcing
how much lap we should provide in columns for Fe-500?
what is lap length?
How many cement mortor dry quantity required for 1m3 ?(1:4)