how much cement,sand,aggregate will use for 1 cum in ratio of
1:2:4.
Answer Posted / roys
Ratio of concrete mix =1:2:4 (Calculation for 1cum)
Cement:-
1/7*1.54=.22 cum [1.54for dry volume]
=.22/0.0345
=6.38bags
Sand:-
2/7*.22=0.06cum
=0.06*35.32
=2.12cft
Aggregate:-
4/7*.22=0.13cum
=0.13*35.32
=4.59cft
| Is This Answer Correct ? | 61 Yes | 24 No |
Post New Answer View All Answers
What you understand by building codes?
What is the wall thickness of NP-3&NP-4 hume pipe as per I.S code
how to find hardness of water?why it should be determined?
What are the steps involved in the concreting process?
how the calculation occurs if i want to mix 1cum of M50 concrete. please calculate every ingredients with detail calculation.
Difference between pre-tensioning and post-tensioning.
How many cum of 9.5mm stone in 1 ton ?
For removal of formwork of simply supported slab / beam from where to start the deshuttering? ( Max Bending moment of the simply supported beam is in the center hence is it required to start from the supports?)
At what point does a circle start losing area when being flattened?
Explain the design for rcc multi-storied building?
How does siphoning work?
What happens to Load at yielding ?
Specific gravity of cement?
Draw the cross section of a boundary wall and label its part with detailing?
The largest size of paper used in plotter to print the drawing made by Autocad .