how cubic feet cement,sand,aggregate required for 1 cubic feet
ratio=1,1.5,3

Answers were Sorted based on User's Feedback



how cubic feet cement,sand,aggregate required for 1 cubic feet ratio=1,1.5,3..

Answer / mohammed aijaz hussain

Volume of concrete = 1 cu.ft.
Volume of Dry concrete = 1.5 X 1 = 1.5 cu.ft.
Volume of cement required = 1/ 5.5 X 1.5 = 0.273 cu.ft.
= 0.22 Bag = 11 kg.
Volume of sand required = 1.5/5.5 X 1.5 = 0.41 cu.ft.
Volume of aggregate = 3/5.5 X 1.5 = 0.82 cu.ft.

Is This Answer Correct ?    19 Yes 8 No

how cubic feet cement,sand,aggregate required for 1 cubic feet ratio=1,1.5,3..

Answer / ratheesh

cement = 7.5 kg
sand = .0076 m3
Aggrigate = .015 m3

Is This Answer Correct ?    16 Yes 9 No

how cubic feet cement,sand,aggregate required for 1 cubic feet ratio=1,1.5,3..

Answer / bharathi

cement - 8.22 Kg
Sand - 0.428 m3
20mm BM- 0.856 m3

Is This Answer Correct ?    4 Yes 1 No

how cubic feet cement,sand,aggregate required for 1 cubic feet ratio=1,1.5,3..

Answer / arunkumar

cement = 3 kg
sand = 0.75 band
20mm metal =1 band

Is This Answer Correct ?    0 Yes 0 No

how cubic feet cement,sand,aggregate required for 1 cubic feet ratio=1,1.5,3..

Answer / balachandra mahendra

cement=8.3
sand=0.414
metal=0.76

Is This Answer Correct ?    0 Yes 0 No

how cubic feet cement,sand,aggregate required for 1 cubic feet ratio=1,1.5,3..

Answer / darshandachchu@gmail.com

cement=403.5kg
fa=.42cum
ca=.84 cum

Is This Answer Correct ?    2 Yes 2 No

how cubic feet cement,sand,aggregate required for 1 cubic feet ratio=1,1.5,3..

Answer / jenu

Cement - 11.65 Kg
Sand - 0.43 cft
20mm - 0.86 Cft

Is This Answer Correct ?    2 Yes 3 No

how cubic feet cement,sand,aggregate required for 1 cubic feet ratio=1,1.5,3..

Answer / r.suresh

cement= 11kg
sand = .012cuft
aggregate=.024cuft

Is This Answer Correct ?    9 Yes 11 No

how cubic feet cement,sand,aggregate required for 1 cubic feet ratio=1,1.5,3..

Answer / n.rajeev

sand = .012cft
coarse aggregate = .024cft
cement = 17.28 kg

Is This Answer Correct ?    6 Yes 8 No

how cubic feet cement,sand,aggregate required for 1 cubic feet ratio=1,1.5,3..

Answer / v.purushotham

Coarse aggregate: 0.96 cu.ft
sand : 0.48 cu.ft
Cement : 13.06 cu.ft

Is This Answer Correct ?    1 Yes 3 No

Post New Answer

More Civil Engineering Interview Questions

What is a tensile strength? What is the tensile strength of wood?

0 Answers  


use 1:1.5:3 concrete footing size 9'9" *9'9" and square 12" and also trapezoidal 22" use of 4 columns. calculate how much amount f concrete use. and also tell me the details about course aggregate and fine aggregate and cement bags use .(note; 20mm coures aggregate use)

1 Answers   CMS,


what is the unit for sbc of soil

4 Answers  


what is the comprasive stranth of brick

3 Answers  


five requirements of infill panels for walls?

0 Answers  






can u plz send me ntpc placement papers(civil engineering) at munjalricha1988@gmail.com and which types of questions are aked by ntpc

10 Answers   HPCL, NTPC,


How to check Diameter of Np2 rcc pipe?

1 Answers  


mean of NH4 pipe

0 Answers   GVK, L&T,


Method for Calculating the WEIGHT OF ANGLE ?

3 Answers  


What is the diff. Between rectangle & parallelogram?

10 Answers  


how to calculate steel for beam of simple home and for heavy buliding ? explain me briefly

3 Answers   CCCL,


why 50% more is assumed while calculating dry volume of coarse and fine aggregates in concrete calculations.whether 50% more is correct? How is it decided? whether the same is applicable to cement volume. Also what about cement mortar dr volume? How much more is to be considered for dry volume of mortar.

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)