Pls. help.
If a contract was awarded to a contractor in april 2012 with
steel & cement base price as rs. 45/kg & 250/bag. Now in
oct. 12 steel cement price becomes 55/kg & 290/ bag. How
escalation will be calculated? Pls. tell complete calculation
Regards,
Answers were Sorted based on User's Feedback
Answer / a.sanjeevakarna
First of all refer the contrctor agrremnt regarding the
Price escalation.
Some Govt sector accept the present rates based on the
invoices of the materials purchased and some accept only
rates approved by the govt every month.
in case of Cement and Steel in A.P. irrigation The
Escalation calculations are calculated as follows.
Cement
Date of Measeurement, Qty of concrete, Cment req as per
Design mix, Qty of Cement Consumed, Base rate + 5%,
Present rate, Present rate - Base rate, Qty of cement X
diff in price is the Escalation Amount.
Please note all above deatils sepaetared by commas are
write in Table Format.
Steel: Same as above.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / viswanadhamklvs
Generally the PVC formula will be given in the Contract
document itself. The month in which the contractor quoted
his bid will be considered as Base month. The indices for
the commodities will be published by the office of Economic
Adviser in the web site eaindustry.nic.in. These index
values shall be substituted in the formulae given against
each commodity viz., steel and cement. In the same fashion,
labour component also shall be considered based on the index
value given by labour Beuro of India.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / vamsi
Price escalation can done after completing of total work. As per MB the quantity of cement and steel usage have to recorded
and see the prices in the relevant work done month later total all cement qnty and steel qnty and multiply cement in Kgs/Cum using the data.
Mail me i will give u the Price Escalation Format.
vamsi.talari@gmail.com
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / jai
The prise quoted by us in the BOQ wil be the finel prise...
| Is This Answer Correct ? | 0 Yes | 1 No |
cement required for construction of 400mm*200mm*200mm concrete solid blocks for 1sq.mtrs,how?
From where the relationship of target strength comes in mix design(graph)
What is the role of a PMC(project management consultancy) in any construction work?
How much steel required for 1000 sq ft slab 4" thickness.
point of contraflaxure
why we use min. 12mm dia bar in a coloum.
7 Answers BPCL Bharat Petroleum,
What is the tensile strength of marble?
what is the ratio of m50 grade in concrete block
silt maximum in sand.
how much grade of concrete can be used for different structural element such as slab,beam,column,footing & plinth beams? and type of cement can be used in construction work & also types of cemnt grades
how can change 10mm dia @275 c/c bar spacing to 12 mm
what is the use of water bar in water tank and is this an extra item in estimate?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)