What should be percentage of silt content in sand?
Answers were Sorted based on User's Feedback
Answer / vijay kumar jayswal
Not More than 8% by Volume Asper Cpwd Specification
| Is This Answer Correct ? | 74 Yes | 10 No |
Answer / naresh kumar n
AS PER IS:383-1970 THE SILT CONTENT SHOULD BE MAX 3% FOR
UNCRUSHED SAND i.e, RIVER SAND AND MAX 15% FOR CRUSHED SAND
i.e, CRUSHED STONE SAND.
| Is This Answer Correct ? | 53 Yes | 8 No |
Answer / md yunus khan
As per Is Codes By Weight Silt Limit Is 3%.
As Per CPWD Codes By Volume Silt Limit Is 8%.
| Is This Answer Correct ? | 36 Yes | 3 No |
Answer / nagesh
I agree that percentage of siltcontent by weight should be
3% and by volume upto 8%, but can anybody tell why the
permissible silt content is 15% for crushed sand.
| Is This Answer Correct ? | 22 Yes | 2 No |
Answer / g varun
AS PER IS:383-1970 for CONCRETE THE SILT CONTENT
1.SHOULD BE MAX 3% FOR UNCRUSHED SAND i.e, RIVER SAND
2.AND MAX 15% FOR CRUSHED SAND i.e, CRUSHED STONE SAND
As per is 2116 for mortor
1.SHOULD BE MAX 5% FOR UNCRUSHED SAND i.e, RIVER SAND
2.AND MAX 5% FOR CRUSHED SAND i.e, CRUSHED STONE SAND
| Is This Answer Correct ? | 18 Yes | 6 No |
Answer / adesh kumar dohare
As per IS 383 Silt percentage in Content of sand minimum 3% and maximum 8%.
| Is This Answer Correct ? | 8 Yes | 1 No |
Answer / g varun
for mortor purpose silt by weight is
5% for natural sand
5% for crushed sand
for concrete purpose silt by weight is
3% for natural sand
15% for crushed sand
| Is This Answer Correct ? | 2 Yes | 1 No |
what is diffence in grade 43 & 53 of cement?
4 Answers KFC, L&T, NICE, Puravankara,
what is the code for classification of bricks
How much steel needed for 1 m3 concrete for slab?
how to caliculate required amount of cement and sand required for 1cu.m.
What is the difference between shear and tensile strength?
What is difference between limit state and working stress method? How it is applies in building structure.
Differenciate between One way slab and two way slab
Are you ready to relocate with your immediate family to United States as a new employee?
how much steel required for 1 sq.m area?
24 Answers AA Architects, L&T,
Why do we provide development length in RCC?
what is the coefficient for running feet to cft coversion both area and price
Please let me know about answer for my Question as "What is the maximum wastage allowable of HYSD Steel in any Bridge project as per Code and Code reference also ?
0 Answers Amit Enterprises, ICT,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)