What is the ratio of cement, sand, aggregate of mix M25
Answers were Sorted based on User's Feedback
Answer / mohammed aijaz hussain
M25 mix of concrete has the proportion of 1:1:2. It is
nominal mix. More rich mix than this will be the design mix.
| Is This Answer Correct ? | 4 Yes | 0 No |
Answer / sandeep dahiya
Nominal mix of Ratio 1:1:2 is equivalent to Design Mix M25
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / md jamirul islam
1(cement):1(Sand):2(Aggregate) for M25 according to IS456-2000
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / mahesh b.jadhav
Nominal Mix concrete may be used for concrete of M20 or lower Grade
If Nominal Mix used for M25 grade concrete it is 1:1:2 & cement consumption will be very department to department as below
CPWD M25 =12.2 Bags/Cu.M.
State PWD M25 =8.5 Bags/Cu.M.
Right way for M25 grade concrting is Design Mix Concreting
| Is This Answer Correct ? | 2 Yes | 1 No |
how to calculate round stirrups.
4 Answers Infinity Engineering,
what is education Cess.
Define road.
what is the basic idea of well sinking????
1 Answers Quality Water Management Systems, Simplex, Sobha Developers,
how can we calculate costing of a project per sqft/sqm
1 Answers Associate Consultant, AVT, L&T,
pls give me some basic informations in construction of a structure?
fluid flow takes place due to its:- viscosity,comprssibility,surface tension,deformation undershear force
what is a moisture correction
2 Answers ITC Infotech, Unity Infraprojects,
how to balance aggregate during mix design of concrete???? how to calculate moisture content like C/A,F/A and how many percentage using ice instead of water for example of we are preparing ice concrete??????
How to find the weight of steel in feet? e.g: dia of steel is (6"') sut. We know that (1" inch 8 sut).
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
when we workout quantities of reinforcement steel , whate are the critari of lap length for column
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)