what is the right method of laying cable tray if we are
using EOT crane in shed, better is below or up
Answer / sufiyan
Definitely if you are using EOT crane then the cable tray must be installed above the height of cross travel of that crane + 0.5 mtr for safety
| Is This Answer Correct ? | 0 Yes | 0 No |
Explain how to determine capacitor tolerance codes?
Cummins 750 KVA generator how much disel consumed per hour and how many units generated on 100% full load.
what is the principle of operation of domestic fan?? what is the role of capacitor in it??
Why the unit sizes of hydro generating machines are not standardized as in case of thermal powerplants?
in 11kv/400v transformer when only one phase of 11kv supply fails what happens to sec voltage and why
What's the difference between a generator using 50Hz and 60Hz? When do we need to use a generator 50Hz and 60Hz?
Given a ckt,the max power dissipated in the load ZL ?
What are the Full Forms of TVM, MTL, CVT ?
what is the disadvantage of lagging power factor & why ?
During a temperature rise test of a bus duct, it is fed with 415 volts at 2000 amperes. Why dont we get an electric shock if we touch the bus bars?
what happen if any one phase of a slipring induction rotor winding is open?is it start or won't?
Please tell me if you are electrical engineer,and you are appointed for the maintainance of Electrical Power plant,then which parts of the plant deal with you.Also tell how these parts/components work.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)