How to calculate CT ratio for 11KV 1500KVA Transformer
500KVA MD and 1400KVA connected load ?
Note:- As per MSEB(Maharastra state electricity Board)
Answer / k.prakashchandra
Max current based on Tr capacity is 79A. hence rated primary
current of ct would be 100A.If development is not expected 75 A
| Is This Answer Correct ? | 5 Yes | 3 No |
What is the operating range of voltage and current in grid supply in India?
How can we check ELCB trip current sensitivity How can we check earth resistance value
At a family reunion were the following people: one grandfather, one grandmother, two fathers, two mothers, four children, three grandchildren, one brother, two sisters, two sons, two daughters, one father-in-law, one mother-in-law, and one daughter-in-law. But not as many people attended as it sounds. How many were there ?
orifice sizing how done, checking & selection
what is subtransient , transient and steady stateac components
What will happen if 230V DC motor connected to 230V AC Supply?
15 Answers Ashok Leyland, BOC, JSW, ONGC, RRB, TRB,
whay we used silica gel in Transformer
What is the necessary condition for stability.
what is the difference between potential transformer and capacitive voltage transformer?
Single line diagram for dbb (double bus bar)system.
for 4 MVA , 33K.V/6.6K.V transformer. secondary side the connected load is 3000H.P. What is the rating of capacitor bank to be insttaled.
can we run AC & DC cables in same tray
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)