curing duration

Answer Posted / girish kumar v k

Gentlemen there is nothing Technical behind the concept of Curing.Logic is what behind this.
As per IS 456, the grade of the concrete itself indicates the strength of the Concrete after 28 days,..right?
Then curing has to be done for 28 days in order to test the Compressive strength of the concrete.
What I would say is.. without curing for 28 days how can you carry out the test and say that the member which contains the concrete equals the strength that off the cube strength. This concept is purelly Illogical.
To ensure whether the member has attained strength, cubes have to be kept on/adjacent to that particular member (Slab, beam,girder,column) and then curing to be carried out. Now curing will happen equally and simultaneoulsy to both.
Afterwhich testing of cubes will actually give the strength of the member
Else If curing is done for 7/14 days then test the cubes only for that particular period, which also signified same strength for the member.
But curing for 7/14 days only would lead following
1. Low compressive strength then required as per Design mix
2. Lesser durability of concrete
3. Increased permeability
4. Concrete becomes brittle & breaks due to improper hydration.

Is This Answer Correct ?    18 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the different approaches in designing the floors of the service reservoirs?

755


how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?

1643


i have to give lap joint fo 1Mtr steel of dia12mm,whenever i did mistake i cut less 5cm plz tell me how much i will give lap joint so that length comes 1Mtr

1542


Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?

2029


Define unit atmospheric pressure? Difference between gauge pressure, absolute pressure?

1677






Why Is Propping Required For Long Structures Once The Form Work Is Removed?

692


pls tell estimate for 1 kilometre length random rubble masonry 0.90 metre height 0.600 metre width

1099


What are the different softwares used for cad?

708


Whats the standard thickness of 20'/30' wide rcc service road and what will be the estimated cost per cubit feet

2347


in plate load test what is the thickness of plate 20mm 5mm 50mm none

1709


What is difference between code and standard and specification?

1795


In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?

1495


What is the difference between tor steel and tmt steel?

648


What is unit weight of normal concrete?

670


Labor requirement for each item needed? Lean Concrete 103.550m3 Concrete for Foundation and Structure 1753.000m3 Expansion joint 288.000m Contraction joint 127.000m Dowel bar 450.000m

1287