curing duration
Answer Posted / girish kumar v k
Gentlemen there is nothing Technical behind the concept of Curing.Logic is what behind this.
As per IS 456, the grade of the concrete itself indicates the strength of the Concrete after 28 days,..right?
Then curing has to be done for 28 days in order to test the Compressive strength of the concrete.
What I would say is.. without curing for 28 days how can you carry out the test and say that the member which contains the concrete equals the strength that off the cube strength. This concept is purelly Illogical.
To ensure whether the member has attained strength, cubes have to be kept on/adjacent to that particular member (Slab, beam,girder,column) and then curing to be carried out. Now curing will happen equally and simultaneoulsy to both.
Afterwhich testing of cubes will actually give the strength of the member
Else If curing is done for 7/14 days then test the cubes only for that particular period, which also signified same strength for the member.
But curing for 7/14 days only would lead following
1. Low compressive strength then required as per Design mix
2. Lesser durability of concrete
3. Increased permeability
4. Concrete becomes brittle & breaks due to improper hydration.
| Is This Answer Correct ? | 18 Yes | 3 No |
Post New Answer View All Answers
How to calculate(Thumb rule) the consumption of steel per cubic meter for different concrete members.
How do you measure water flowing through 300mm diameter pipes?
Define What is the difference between routing maintenance and major maintenance in school facilities?
what is the difference between natural draught cooling tower and induced draught cooling tower
What is meant by dimensioning?
During reclamation how can the occurrence of mud waves can be rectified?
For what purpose bedding is used under storm water drains, explain?
What things you need to take care of before building a kitchen island?
What is a kip?
CAN V USE CRUSH SAND FOR CLAY BRICK MASONARY
what is civil engineer greatest strength and weakness?
50 acre of land to be reclaimed for an average height of 2.5 mt. Dredging area is 500mx200m size. what is the dredging depth required to reclaim the area?
Detection of a beam & a girder are––––
how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation
Basic questions of civil engineering