curing duration
Answer Posted / girish kumar v k
Gentlemen there is nothing Technical behind the concept of Curing.Logic is what behind this.
As per IS 456, the grade of the concrete itself indicates the strength of the Concrete after 28 days,..right?
Then curing has to be done for 28 days in order to test the Compressive strength of the concrete.
What I would say is.. without curing for 28 days how can you carry out the test and say that the member which contains the concrete equals the strength that off the cube strength. This concept is purelly Illogical.
To ensure whether the member has attained strength, cubes have to be kept on/adjacent to that particular member (Slab, beam,girder,column) and then curing to be carried out. Now curing will happen equally and simultaneoulsy to both.
Afterwhich testing of cubes will actually give the strength of the member
Else If curing is done for 7/14 days then test the cubes only for that particular period, which also signified same strength for the member.
But curing for 7/14 days only would lead following
1. Low compressive strength then required as per Design mix
2. Lesser durability of concrete
3. Increased permeability
4. Concrete becomes brittle & breaks due to improper hydration.
| Is This Answer Correct ? | 18 Yes | 3 No |
Post New Answer View All Answers
what is concrete canvas?
types of piles detail,
How long does it take concrete to harden?
crank types
what is mc arther pile?
Can anyone tell me the sequence of the activities in a drawing room, kitchen & Toilet including civil work, finishing, electrical & plumbing fittings
How to determine dia of steel for use in column,slab etc. i mean how to calculate the diameter of steel which is to be used in structures.
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
Minimum concrete cover in slabs, columns, beams, foundation and other st?
five requirements of infill panels for walls?
material used for mendrel use to bend epoxy coated rebar
Process of pcc in wateredug
undistributed samples are obtained by
how to take concrete quantity for precast segment for viaduct project?
what is difference between GTS bench mark and temporary bench mark