in the construction field why hook up s.s.tubing for
transmitter using upto 6mtrs of closed loop, but y not
open loop nomore restriction
Answers were Sorted based on User's Feedback
Answer / s
Hook-up Diagram having installation details like
vaves,tee,elbow sizes.It is a detailed diagram for
Particular equipment installation which is not available in
P&ID.
Is This Answer Correct ? | 5 Yes | 1 No |
Answer / chepin
S answer is right. Could some one pls share sample of the
hook up drawing.
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / www.islamqa.com
I think it's related to system response time, 6 meters
limitation to make the feedback pressure signal built up
through the pipeline and arrive to I/P or controller in
suitable time.
open loop has no feedback so there's no limitations.
Regards,
Ahmed Sabry
Control and Instrumentation Engineer
GPC - General Petroleum Company
ahmedsabry.online@gmail.com
CELL.: 00 2 0121367310
Is This Answer Correct ? | 0 Yes | 0 No |
If I want to buy a pressure switch & 3-way valve for hot water application then witch parameter I should consider.
what is modbus?and why use it?what benifit
on which principle control valve works?
How LVDT position transmitter works on DC supply(24vdc) from DCS, whereas transformer operates on AC supply? pls help..
how can calibrate vacume trasmitter by HART COMMUNICATOR ?
Why MUX JB's are using only Temperature Element in Fundation field bus?
0 Answers Reliance Industries,
How much Resistance Show by RTD(PT100) when it is installed in process(Consider Process Fluid temp 29 Deg C)?
kindly sent some demo question and answer
Explain PID controller tuning & any one method used for it.
What is the difference between modbus,fieldbus & profibus
Tell me the field calibration procedure step by step with diagram of temperature transmitter, temperature indicator, flow indicator, level indicator, control valve, thermocouple, pressure indicator (digital & analogue).
how to do loop checking pls email to shanavaska2000@yahoo.com