Basic philosophy of applying 3P tripping for uptill 132KV
switchyards & for 132KV & above 1P/3P tripping is used.
Answer / chandrasen mourya
Because most of the line used for transmission by EB are of
220 & 400kV . These lines are of lenght greater then 50 kms.
Due to which any arcing fault which is temp can trip the
line & total suhtdown. The 1p/3p trip with single shot or
multi shot AR is provided in 132kv & above.
| Is This Answer Correct ? | 0 Yes | 2 No |
Is it required to lay 2 runs of GI wires along with armoured cables from one power DB Machines of higher rating?
Why the brushes used in dc machines are made of carbon not from other metal?
why we used stone chips under the transformer area..
What is power factor?
what are the factors to be considered while design the breaker either HT or LT??
Does magnetomonopoles exists? one maxwell equation strongly suggests no, but how about their existance in plasma?
opkinson's test
how many poles we use in high power generation
When do you use a VFD motor?
What is mean by hot and cold loop testing?
Does human body can effect the electric shock when stand on Insulated material?
how to test the ht machines?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)