Answer / v.sivakumar
Scheduling can be done in two areas
1. Infoview (which is explained in the before answer)
2. Through CMC (Central management console)
steps followed
1. Create a calendar according to your requirement.
2.Select the schedule tab in the object which you want to
schedule.
Note: In CMC object referes to report.
3.specify the destination
4.specify the format
5.select the calendar in the scheduling option and lookup
the calendar what you created for this requirements
6.schedule it
for more clarification mail me
Is This Answer Correct ? | 12 Yes | 1 No |
Answer / abhishek
HI all
For sheduling any report open info view as admin
privilage ,then each and every reprot having a sheduling
option which is like a tab in bottom of each report click
on it then there is new window apper fill its all filed
like its sheduling time,its destination folder etc
Is This Answer Correct ? | 13 Yes | 4 No |
Answer / neetu
Scheduling in BO XI R2 cab be done using infoview.Below
mentioned are the steps to follow
1.Open the appropriate folder of the report.
2.Towards the right side of the panel you can see the
reports available.
3.Below the report name "Schedule " option is available
along with History,properties.modify.
4.click on Schedule
5.A new window will pop up
6.Enter the details i.e When,Destination,Format etc.
7.Finally click on Schedule button.
The report will be scheduled
Is This Answer Correct ? | 6 Yes | 1 No |
Answer / arabandisowmya
To Schedule a Web I document:
1. Locate the report you want to schedule.
2. Click schedule under the report link.
3. Select options
1. When
2. Destination
3. Format
4. Caching options(you can export the document as excel,
standard HTML, or PDF)
4. Click Schedule
Is This Answer Correct ? | 3 Yes | 1 No |
Answer / guest
XIR2 scheduling the report using scheduler in
administrator(Supervisor module).
Is This Answer Correct ? | 4 Yes | 9 No |
How to create a tooltip in Webi? Is there a way to create Tooltips in Webi reports for non- hyperlinked columns? Users should be able to hover over a value in a column in the report and that should show a tooltip box with more detail regarding that column value. This is possible when you hyperlinked the column,Is it possible when you dn't have hyperlinking? Thanks in advance.
what is confirm dimension ?
How to link one location universe to other location universe
what is fantrap ?
If any one Deleted the BOMain key by accidently,is any possible to get back that Bomain key.if possible please send some steps.
Once the project is submited to the Client. Client says that report is taking long time to run? Where u need to check?
How do u Receive requiremnts from the client?
What is Custom Sorting? In development environment we had applied custom Order on Month which is having the following list of values September,October,March,August and December only.But in Production environment Month is having all LiSt of Values like 12 MOnths(Jan to Dec).So ,How it will effect the Sorting in production environmentof universe and as well as in reporting????? Thanks in advance.
HI, Can any body explain me ? If we careate objects using derived tables it will decreasess the performence? If we are not creating the objects using the derived tables then what is the use of having the derived tables?
can u create report to connect oracle and sqlserver at a time?
use scheduler to refresh report.....explain please.....
How to create an popup in the WEBI report if the report is showing partial result?