Transfrmer has
1. routine tests
2. type test
3. special test
further type tests are
1. IR OF WINDINGS
2. POLARITY
3. VOL. RATIO
4. TEMP RISE TEST
5 DIELECTRIC LOSS
| Is This Answer Correct ? | 21 Yes | 5 No |
Answer / hitesh tiwari
1. IR VALUE TEST
2. MAGNETIC BALANCE TEST
3. MAGNETISING CURRENT TEST
4. VECTOR GROUP TEST
5. WINDING RESISTANCE TEST
6. OPEN CKT TEST
7. SHORT CKT TEST
8. TAN DELTA TEST
9. XMER OIL BDV TEST
| Is This Answer Correct ? | 7 Yes | 3 No |
1.insulation resistance test
2.ratio test
3.short circuit test
4.open circuit test
5.back to back test
6.oil testing
| Is This Answer Correct ? | 4 Yes | 3 No |
Answer / manoj patel
1) Ratio & tap continuity test
2) megger test
3) Magnetic balance test
4) vector group test
5) Inrush current mesurement test
6) Xmer oil BDV test
| Is This Answer Correct ? | 2 Yes | 1 No |
Answer / j.kesavan
dielectricbreakdowntest
acidneutralizationtest
sedimenttest
interfacial tensiontest
parts per million moisture test
colour and visual partical test
dissolved gas test
| Is This Answer Correct ? | 3 Yes | 3 No |
Answer / m.ravi
three types
1. o.c test
2. s.c test
3. back to back test
| Is This Answer Correct ? | 3 Yes | 3 No |
Answer / ksn murthy ,j.e,electrical
IR Values, Change of Siclikazal, any oil leakages, checking
of HT Lt side Insulator washers, Both Ht Side and lt side
cable terminations. Tx. Body Earth and as well Neutral earth
this is comes to transformer testing this is as per my
knowledge if any mistakes please excuse me.
| Is This Answer Correct ? | 0 Yes | 0 No |
For 7.5kw star delta starter how to calculate 1. Mccb rating 2. Contactor rating 3. Over load relay rating
how can we know the size of cable cross-section from current rating ?
what can be the causes of capacitor start motor having a higher current that its actual
how we can check new PT ? without name plate.
1 Answers Indo Power Projects,
How to connect a ELCB with contactor and relay ?
Why do we choose 33kV transmission for industrial purpose and 11Kv for township?
What is mean by INRUSH CURRENT?
what are the usual topology of transformers at different substations in the power system and why that particular topology is choosen. what are the limitaions of that topology?
This is reqd for a 1MW Solar power plant..We have 2DC outputs from the solar panels Connected to 2INVERTOR panels.. Output from invertor is 3ph,280v,500kva,50hz.These are connected to individual ACB.This has to be stepped up to 11KV ,1250KVA SYSTEM.Now can I use (1) one more ACBTO GIVE A COMBINED OUTPUT OF 1000KVA,280V & STEP UP THE OUTPUT BY USING a single two winding 3 ph transformer 11kv/1250kva. or (2)use the two outputs and connect to one three winding transformer of above rating..Pls suggestwith details.
Define super node?
what is the meaning of DY-11 Z-5%
Why rotating machines are not allowed to run near critical speed region?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)