Answer / bhadresh dhora
One and Half breaker means.... Two breaker serve the pupose of three bays. Example : For Large capacity generator Two breakers one Main and another Middle.. Both breaker function Generator, Line and option with one of them can be isolated that is three pupose and two breakers i.e 3/2 = 1.5 i.e One and Half breaker.
| Is This Answer Correct ? | 8 Yes | 8 No |
How to identify the start and end of 3phase 12 lead motor if U1, U2, etc numberings are lost or erased.
What is a soft start?
how to find the transformer neutral copper earthing size
How to calculate the no of Ceiling fan (1200mm sweep) per unit area?
how does this job compare with others you have aplied for?
WHAT IS THE FAULT WHEN 100HP TURBINE MOTOR TRIPS, LIST THE FAULTS AND ITS TRABULESHOOTING TIPS.. MY AUTO TARNSFORMER STARTER TRIPS
why in transformer there is not rotating fiddl/ magnetic field like motor
can we replace d.c.motor by 3 phase induction motor for a particular application
Why power factor is arising in electrical circuit, is it possible to eliminate from the circuit, why
how we can calculate which capacity capacitor bank we have to add for improve pf?
3 Answers Consultancy, JM Huber, Torrent Power,
Define CT & its function
how can testing using megger?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)