How the main bus bar rating of 400kV switchyard with one
and half breaker scheme is calculated.
Answers were Sorted based on User's Feedback
Answer / bhadresh dhora
One and Half breaker means.... Two breaker serve the pupose of three bays. Example : For Large capacity generator Two breakers one Main and another Middle.. Both breaker function Generator, Line and option with one of them can be isolated that is three pupose and two breakers i.e 3/2 = 1.5 i.e One and Half breaker.
| Is This Answer Correct ? | 8 Yes | 8 No |
why electric shock due to dc is dangerous than that of ac
xpression 'document.FrmQF.myemail' [
How to select Main CB Rating for 187 KW Load?
Readings of ER300P Trivector meter
"What is the difference between voltage and potential differnce?"
Can anyone explain me about the RLC based Impulse high voltage generator and how to and operation of Series resonant High voltage reactor...?
why we do occ & scc test in transformer ?how we can do it ?
why table fans rotate clockwise .while ceiling in anti clockwise?
how to calculate the speed of a induction motor without using tacho meter?
is any body explain me why return current in three phase power system is less then in a red, yellow, blue phases??? as we know Ir+Iy+Ib=In then why nutral wire has less then phase current????
heat can flow from a body at low temperature to a body at higher temperature only when ........ is supplied from an external source A). Voltage B). Current C). work D). Mass
how to find impedance , mutual indatnce in transmission lines
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)