To calculate CFM for any unit or say a room with dimensions
as L x B X H.... then for this room the total CFM for air
duct should be equal to
1. Total Volume x 6 .............. for Private Room
2. Total Volume x 12 .............. for Public Room
Is This Answer Correct ? | 29 Yes | 13 No |
Answer / thowsif s
For 175 Sq. feet the Cooling required is 1 TR...
Is This Answer Correct ? | 16 Yes | 7 No |
Answer / nikunj faldu
for room size 10ft.x10ft.x10ft.= 1ton capacity unit
requierd & airconditioner are not suck a alwege fresh air,
it's circulate of room air, so not required any exhaust &
never provid otherwise we never get a cooling. & ti's
mesurment in cubic feet.(for room volume).
Is This Answer Correct ? | 12 Yes | 3 No |
Answer / rupesh
how to calculate the rating of motor required in 10000cfm
for industrial area.
Is This Answer Correct ? | 2 Yes | 0 No |
I will explain you with an example : If 10 x10x 12 feet room means you can calculate C1 = 10x10x12 = 1200 BTU/Hr and Multiply the same with co efficient 6 = 7200 BTU/Hr. & If 2 person going to occupy the room means each person 500 BTU/hr. C2 = 2 persons x 500 BTU/hr = 1000 BTU/hr. (C1+C2) BTU = 8200 BTU/hr. 12000 BTU/hr = 1 Ton. Hence Upto 1200 BTU/hr we can go for 1 ton AC.
Is This Answer Correct ? | 2 Yes | 0 No |
What is a BBS?Find out the cutting length for a 300*300 column with 40 mm cover?
21 Answers L&T, SSC,
What is the difference between yeild strength and compressive strength of steel???
what is the logical concrete mix design for M 30 Grade and the cement consumption per M3
what is the process of repair the structure in whitch reinforcement is open
how lap length is increased with increase of Grade of steel?
For what building Built-on balconies are preferable? What are the advantages?
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
how to calculate 1:2:4 ratio concrete cement, sand, metal and water please give me brief calculation
34 Answers Call Centre, CCCL, Oracle, RLM, RPP, Sunanda Infra, Sunrise Enterprises,
How to calculate canal slope curvature qty!
wat happens to the foundation when only live & dead loads are considered( wind load is excluded) during the design of tall structures. options are: a)only settlement in the internal structure and not external structure b)only settlement in the external structure and not internal structure c)no differential settlement d)none of the above
4 Answers BBJ Construction, IOCL,
Anyone have sample questions for bhel please send me since Iam appearing for this exam. Kindly send this to my e-mail: nethaj_babu@yahoo.co.in
What is difference between FE-415 and FE-500???